Special instructions
- pi0 running
- 300 nA beam current
- TAGH_HV_ProductionSpring2023_300nA.snap
Run conditions
- Radiator: 4.5 E-4 Al (amo, on the goniometer)
- Collimator: 5.0 mm
- TPOL converter: Be 75 um
- Runs are no more than 2 hours (~400M triggers)- see whiteboard for the production cycle
- Target: Liquid Hydrogen
- DAQ configuration - see whiteboard
Current Experiment
GlueX II (with DIRC) & JEF and Alpha
- Experiment numbers: E12-12-002, E12-12-002a
- GlueX II Proposal
- Alpha Proposal
- Spokesperson: M Shepherd
- In the BTM this is "GlueX 2 / JEF"