Difference between revisions of "Short Term Run Plan"
From Hall D Ops Wiki
(→Current Experiment) |
|||
Line 7: | Line 7: | ||
== Current Experiment == | == Current Experiment == | ||
− | + | GlueX II (with DIRC) & JEF and Alpha | |
− | * Experiment | + | * Experiment numbers: E12-12-002, E12-12-002a |
− | * [https://misportal.jlab.org/mis/physics/experiments/viewProposal.cfm?paperId=834 Proposal] | + | * [https://misportal.jlab.org/mis/physics/experiments/viewProposal.cfm?paperId=834 GlueX II Proposal] |
− | * | + | * [https://arxiv.org/abs/2405.01288 Alpha Proposal] |
+ | * Spokesperson: M Shepherd | ||
* In the BTM this is "GlueX 2 / JEF" | * In the BTM this is "GlueX 2 / JEF" |
Revision as of 12:11, 15 April 2025
Last updated 3 April 2025
Special instructions
Current Experiment
GlueX II (with DIRC) & JEF and Alpha
- Experiment numbers: E12-12-002, E12-12-002a
- GlueX II Proposal
- Alpha Proposal
- Spokesperson: M Shepherd
- In the BTM this is "GlueX 2 / JEF"
Run conditions
- Radiator: 4.5 E-4 Al (amo, on the goniometer)
- Collimator: 5.0 mm
- TPOL converter: Be 75 um
- Runs are no more than 2 hours (~400M triggers)- see whiteboard for the production cycle
- Target: Liquid Hydrogen
- DAQ configuration - see whiteboard