==Collect More Regular Data==
 
==Collect More Regular Data==
# Goal: Collect data for calibration and characterization of the detector.
+
# Goal: Commission the trigger Collect data for calibration and characterization of the detector.
 
# Responsibility: HallD
 
# Responsibility: HallD
 +
* Expected Schedule: See start dates in the run coordination meeting pages [https://halldweb1.jlab.org/wiki/index.php/Run_Coordination_Meetings#Meeting_General_Agenda here] and the general schedule [https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan#Run_Plan here]. Duration of the  Regular Data Collection: 9.5 days
 
# Conditions:
 
# Conditions:
 
#* Tagger hall equipment in place and operating.  
 
#* Tagger hall equipment in place and operating.  
#* Beam 50nA CW
+
#* Beam 50 - 100 nA CW
#* Radiator is 10<sup>-4</sup>.
+
#* Radiator is 0.2 - 1.0 10<sup>-4</sup>.
#* Collimator hole is 3.5mm.
+
#* Collimator hole is 5 mm.
 
#* Solenoid 1200A.  
 
#* Solenoid 1200A.  
 
#* GlueX detectors are on.
 
#* GlueX detectors are on.
#* Thin commissioning target at various positions.
+
#* Commissioning targets at various positions.
 
# Activities
 
# Activities
#* If time permits, and all other tasks are done
+
#* Commission the trigger [[https://halldweb1.jlab.org/wiki/index.php/Trigger_Commissioning trigger commissioning page ]]: Expert: A. Somov
#* Take enough data for preliminary calibration and alignment of the detector. At least one week of running.
+
#* Take data with the expected "low intensity" conditions of 10 MHz/GeV photons: 100 nA, 10<sup>-4</sup> RL radiator, 5 mm collimator and the 10 mm plastic target at the regular position. These conditions are close to the "low intensity" settings of GlueX experiment. Verify the rates and backgrounds. 1 shift.
 +
#* Take data for preliminary calibration and alignment of the detector: the rest of the scheduled time.
  
 
[https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page]
 
[https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page]

Latest revision as of 10:19, 20 October 2014

Collect More Regular Data

  1. Goal: Commission the trigger Collect data for calibration and characterization of the detector.
  2. Responsibility: HallD
  • Expected Schedule: See start dates in the run coordination meeting pages here and the general schedule here. Duration of the Regular Data Collection: 9.5 days
  1. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50 - 100 nA CW
    • Radiator is 0.2 - 1.0 10-4.
    • Collimator hole is 5 mm.
    • Solenoid 1200A.
    • GlueX detectors are on.
    • Commissioning targets at various positions.
  2. Activities
    • Commission the trigger [trigger commissioning page ]: Expert: A. Somov
    • Take data with the expected "low intensity" conditions of 10 MHz/GeV photons: 100 nA, 10-4 RL radiator, 5 mm collimator and the 10 mm plastic target at the regular position. These conditions are close to the "low intensity" settings of GlueX experiment. Verify the rates and backgrounds. 1 shift.
    • Take data for preliminary calibration and alignment of the detector: the rest of the scheduled time.

Back to main Fall14 commissioning page