<p style="color:red"> Since the incorrect installation/removal process will cause serious damage to the fiber or PMT, as the first step of this operation, one must obtain permission from Justin Stevens.</p>  
 
<p style="color:red"> Since the incorrect installation/removal process will cause serious damage to the fiber or PMT, as the first step of this operation, one must obtain permission from Justin Stevens.</p>  
 
+
* Due to the fact the South DIRC box c2r18 doesn't have RTV cookie, therefore, a special installation and uninstallation procedure is required, installation is given: https://logbooks.jlab.org/entry/3860930. (This is for documentation only donot use)
 
+
* See update-to-date instruction: https://logbooks.jlab.org/entry/3862103
* Due to the fact the South DIRC box c2r18 doesn't have RTV cookie, therefore, a special installation and uninstallation procedure is required, installation is given: https://logbooks.jlab.org/entry/3860930
+
 
+
 
+
* See new instruction: https://logbooks.jlab.org/entry/3862103
+

Latest revision as of 15:50, 8 January 2021

Instruction on Special Procedures and Operations

Fixes to complicated Issues

Status of voltage.png

Symptom of the problem:

Solution

  • General -> Status of Voltages and then “RESET INTERLOCK” for D2_8_MID (picture below).


Installation and uninstallation of South DIR Box c2r18

Since the incorrect installation/removal process will cause serious damage to the fiber or PMT, as the first step of this operation, one must obtain permission from Justin Stevens.