==[[Fall 2014 Commissioning Plan#Drift Chamber Alignment|Main Page]]==
 
 
==[[Tune Electron Beam]]==
 
==[[Tune Photon Beam]]==
 
==[[One Week Pause in Running]]==
 
==[[Collect Beam Data for Detector Checkout]]==
 
==[[Optimize Detector Settings]]==
 
 
==Drift Chamber Alignment==
 
==Drift Chamber Alignment==
 
# Goal: Collect data with no or low field.
 
# Goal: Collect data with no or low field.
Line 21: Line 13:
 
#* If time permits, collect data with target in several positions.
 
#* If time permits, collect data with target in several positions.
  
==[[Collect More Regular Data]]==
+
[https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page]

Revision as of 10:12, 21 August 2014

Drift Chamber Alignment

  1. Goal: Collect data with no or low field.
  2. Responsibility: HallD
  3. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 10-4.
    • Collimator hole is 3.5mm.
    • Solenoid 0-300A depending on backgrounds.
    • GlueX detectors are on.
    • Thin commissioning target at various positions.
  4. Activities
    • If time permits, collect data with target in several positions.