Difference between revisions of "Procedure installing solid target"
From Hall D Ops Wiki
(Created page with "== Procedure to install/change solid targets == Experts: Matt Marchlik, Alexandre Deur, Tim Withlatch Two persons are necessary for the task. Ask Tom Carstens ahead of time ...") |
(→Procedure:) |
||
Line 11: | Line 11: | ||
#Remove the beam profiler if necessary | #Remove the beam profiler if necessary | ||
#Put protective cover on the beam pipe vacuum window | #Put protective cover on the beam pipe vacuum window | ||
+ | #Take the the target tube with the desired target mounted on |
Revision as of 17:03, 12 September 2014
Procedure to install/change solid targets
Experts: Matt Marchlik, Alexandre Deur, Tim Withlatch
Two persons are necessary for the task. Ask Tom Carstens ahead of time for the beam pipe vacuum window protective cover.
Procedure:
- If needed, request Radiological survey of the target area
- Remove the beam profiler if necessary
- Put protective cover on the beam pipe vacuum window
- Take the the target tube with the desired target mounted on