[[Fall 2014 Commissioning Plan]]
 
==Tune Electron Beam==
 
# Goal: Get electron beam to the dump in the tagger hall.
 
# Responsibility: Accelerator, HallD, RadCon.
 
# Conditions:
 
#* Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
 
#* Pulsed beam may be used.
 
#* No radiator installed.
 
#* Collimator blocks the photon beamline to Hall D.
 
# Activities:
 
#* Tune beam to the dump, check the beam specification.
 
#* Check radiation levels in the tagger hall.
 
#* Check for photons and radiation levels in the collimator cave.
 
  
==[[Tune Photon Beam]]==
+
* Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels.
==[[One Week Pause in Running]]==
+
* Priority: High
==[[Collect Beam Data for Detector Checkout]]==
+
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)]
==[[Optimize Detector Settings]]==
+
* Expected duration:
==[[Drift Chamber Alignment]]==
+
# 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
==[[Collect More Regular Data]]==
+
# 3 days:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).
 +
* Prerequisites:
 +
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <span style="font-size:21px">☑</span>
 +
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
 +
# Amorphous radiator ladder equipped and operational <span style="font-size:21px">☑</span>
 +
#* Responsibility: Hovanes Egiyan.
 +
# Beam lines under vacuum <span style="font-size:21px">☑</span>
 +
# Tagger magnet operational <span style="font-size:21px">☑</span>
 +
#* Responsibility: MCC
 +
# Shielding walls installed <span style="font-size:21px">☑</span>
 +
# Radiation monitors installed and operational <span style="font-size:21px">☑</span>
 +
#* Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
 +
#* [https://hdops.jlab.org/wiki/index.php/How_to_read_temporary_CARMS Procedure to monitor CARMs]  
 +
# Upstream Profiler installed in front of the collimator <span style="font-size:21px">☑</span>
 +
# Downstream Profiler installed in front of photon beam dump <span style="font-size:21px">☑</span>
 +
 
 +
* Conditions:
 +
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 &micro;A (average 60-150 nA) for the beam tune
 +
# CW beam 50-100 nA at the final stage of the procedure
 +
# Primary collimator block in the position between two holes, shielding the central area of the beam pipe <span style="font-size:21px">☑</span>. Secondary collimator removed. <span style="font-size:21px">☑</span>
 +
#* Responsibility: Hovanes Egiyan.
 +
#* [[Beam_Line_Detectors_Shift#Move_Collimator | Procedure for moving Primary Collimator]]
 +
# Vacuum window covers removed (7 window covers)  <span style="font-size:21px">☑</span>
 +
# No radiator inserted. <span style="font-size:21px">☑</span>
 +
#* Responsibility: Hovanes Egiyan.
 +
#* [[Tagging_Spectrometer_Shift#Move_Amorphous_Radiator | Procedure for inserting/removing amorphous radiators]]
 +
# No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.
 +
 
 +
[https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page]

Latest revision as of 10:58, 22 October 2014

  1. 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. 3 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D.
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped and operational
    • Responsibility: Hovanes Egiyan.
  4. Beam lines under vacuum
  5. Tagger magnet operational
    • Responsibility: MCC
  6. Shielding walls installed
  7. Radiation monitors installed and operational
  8. Upstream Profiler installed in front of the collimator
  9. Downstream Profiler installed in front of photon beam dump
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. Primary collimator block in the position between two holes, shielding the central area of the beam pipe . Secondary collimator removed.
  4. Vacuum window covers removed (7 window covers)
  5. No radiator inserted.
  6. No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.

Back to main Fall14 commissioning page