==Tune Electron Beam (Time estimate: 15 days)==
 
 
* Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels.
 
* Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels.
 
* Priority: High
 
* Priority: High
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)]
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)]
 
* Expected duration:  
 
* Expected duration:  
# Sept 19 - Sept 29: Tune beam to Hall D line dumplette (Tagger Hall can remain open).  
+
# 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).  
# Sept 29 - Oct 3 2014:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
+
# 3 days:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
 
* Prerequisites:
 
* Prerequisites:
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>
+
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <span style="font-size:21px"></span>
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
# Amorphous radiator ladder equipped (HARP included) and operational <math>\Box</math>
+
# Amorphous radiator ladder equipped and operational <span style="font-size:21px"></span>
 
#* Responsibility: Hovanes Egiyan.  
 
#* Responsibility: Hovanes Egiyan.  
#* <span style="color:#ff00ff">Procedure for radiator harp scans </span>
+
# Beam lines under vacuum <span style="font-size:21px"></span>
# Beam lines under vacuum <math>\Box</math>
+
# Tagger magnet operational <span style="font-size:21px"></span>
# Tagger magnet operational <math>\Box</math>
+
 
#* Responsibility: MCC
 
#* Responsibility: MCC
# Shielding walls installed <math>\Box</math>
+
# Shielding walls installed <span style="font-size:21px"></span>
# Radiation monitors installed and operational <math>\Box</math>
+
# Radiation monitors installed and operational <span style="font-size:21px"></span>
 
#* Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
 
#* Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
#* <span style="color:#ff00ff">Procedure to monitor CARMs </span>
+
#* [https://hdops.jlab.org/wiki/index.php/How_to_read_temporary_CARMS Procedure to monitor CARMs]
#* <span style="color:#ff00ff">Procedure to monitor Halo Counters </span>
+
# Upstream Profiler installed in front of the collimator <span style="font-size:21px">☑</span>
# Primary collimator block in the position between two holes, shielding the central area of the beam pipe <math>\Box</math>. Secondary collimator removed. <span style="font-size:21px">☑</span>
+
# Downstream Profiler installed in front of photon beam dump <span style="font-size:21px"></span>
#* Responsibility: Hovanes Egiyan.
+
#* <span style="color:#ff00ff">Procedure for moving Primary Collimator </span>
+
# First Profiler counter installed in front of the collimator <math>\Box</math>
+
# Second Profiler counter installed in front of photon beam dump <math>\Box</math>
+
  
 
* Conditions:
 
* Conditions:
 
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 &micro;A (average 60-150 nA) for the beam tune
 
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 &micro;A (average 60-150 nA) for the beam tune
 
# CW beam 50-100 nA at the final stage of the procedure  
 
# CW beam 50-100 nA at the final stage of the procedure  
# No radiator inserted. <math>\Box</math>
+
# Primary collimator block in the position between two holes, shielding the central area of the beam pipe <span style="font-size:21px">☑</span>. Secondary collimator removed. <span style="font-size:21px"></span>
 
#* Responsibility: Hovanes Egiyan.  
 
#* Responsibility: Hovanes Egiyan.  
#* <span style="color:#ff00ff">Procedure for inserting/removing amorphous radiators </span>
+
#* [[Beam_Line_Detectors_Shift#Move_Collimator | Procedure for moving Primary Collimator]]
# Hall D controlled quadrupole MQPAD00 turned off. <math>\Box</math>
+
# Vacuum window covers removed (7 window covers)  <span style="font-size:21px"></span>
#* Responsibility: MCC
+
# No radiator inserted. <span style="font-size:21px"></span>
# No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tunning procedure at the MCC.
+
#* Responsibility: Hovanes Egiyan.
 
+
#* [[Tagging_Spectrometer_Shift#Move_Amorphous_Radiator | Procedure for inserting/removing amorphous radiators]]
==[[Tune Photon Beam]]==
+
# No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.
  
==[[One Week Pause in Running]]==
+
[https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page]
==[[Collect Beam Data for Detector Checkout]]==
+
==[[Optimize Detector Settings]]==
+
==[[Drift Chamber Alignment]]==
+
==[[Collect More Regular Data]]==
+

Latest revision as of 10:58, 22 October 2014

  1. 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. 3 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D.
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped and operational
    • Responsibility: Hovanes Egiyan.
  4. Beam lines under vacuum
  5. Tagger magnet operational
    • Responsibility: MCC
  6. Shielding walls installed
  7. Radiation monitors installed and operational
  8. Upstream Profiler installed in front of the collimator
  9. Downstream Profiler installed in front of photon beam dump
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. Primary collimator block in the position between two holes, shielding the central area of the beam pipe . Secondary collimator removed.
  4. Vacuum window covers removed (7 window covers)
  5. No radiator inserted.
  6. No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.