Summary0000193: Install UPS power distribution panel in hall
DescriptionAfter UPS installed run power line to distribution panel in the hall.
Additional InformationNeed to decide on what kinds and how much power is needed.
TagsNo tags attached.
Work by outside group for Hall DNo
Estimated man-weeks2
Percentage complete0
Actual man-weeks0
Attached Files

- Relationships
child of 0000194resolvedhovanes Install UPS in the rack room 

-  Notes
(0000297)
wolin (administrator)
2012-02-01 09:01

I will contact Giles and Tim on this.
(0000301)
wolin (administrator)
2012-02-02 10:51

After talking with Rebecca there may be a snag. She's not sure we'll be allowed to run power from one grid, the Counting House, to a different grid, the hall. I will try to get Tim to get Giles to figure this out.

If we cannot run UPS power to the hall from the Count House we'll have to use separate UPS's in the hall, most likely multiple small ones instead of one large one.
(0000304)
wolin (administrator)
2012-02-06 17:27

No problem running power to hall according to Paul Powers.

Tim says Giles is now in charge of installing the UPS in the Rack Room and running circuits to the Counting House and hall. He will collect requirements for the hall to see if running power there is necessary...we might get away with small UPS's here and there. Running UPS power to a panel in the hall might be expensive, much more than the cost of small UPS's.

But note that small ones must be replaced every two years!
(0000305)
wolin (administrator)
2012-02-06 17:27

Waiting for Giles to collect requirements.
(0000346)
wolin (administrator)
2012-04-04 17:45

Harris will run power from utility room to rack room later this week or early next week. Tom will move UPS into counting house by then.
(0000354)
wolin (administrator)
2012-04-06 13:54

Fernando is strongly against running UPS power to the hall, he prefers to locate FCC Class B UPS's wherever needed. Giles will work out the cost to do this compared to running power from the counting house UPS (Class A) to the hall. Note that Paul and Walt claim that small UPS's must be replaced every two years, although some people dispute this.
(0000494)
wolin (administrator)
2013-03-20 18:03

Almost decided to run power from UPS in Rack room to hall using line filters to bring the power to FCC Class B specs. Giles is responsible. Will likely happen this fall.
(0000538)
wolin (administrator)
2013-06-14 10:56

Waiting for hall to be ready for power upgrade and for Giles to design the UPS distribution system.
(0000555)
wolin (administrator)
2013-07-18 09:15

Transformers in, need to be hooked up. Panels are next, then wiring from the panels. We likely will run the UPS power at that time.
(0000563)
wolin (administrator)
2013-07-26 15:59

Tim wants requirements after the solenoid test. Need to meet with Dave B and query everyone else.
(0000565)
wolin (administrator)
2013-07-26 16:25

I sent email to the collaboration, maybe someone will respond...
(0000575)
wolin (administrator)
2013-09-09 17:17

Waiting for design by Giles.

- Issue History
Date Modified Username Field Change
2012-02-01 09:01 wolin New Issue
2012-02-01 09:01 wolin Work by outside group for Hall D => No
2012-02-01 09:01 wolin Estimated man-weeks => 2
2012-02-01 09:01 wolin Percentage complete => 0
2012-02-01 09:01 wolin Actual man-weeks => 0
2012-02-01 09:01 wolin Status new => assigned
2012-02-01 09:01 wolin Assigned To => wolin
2012-02-01 09:01 wolin Note Added: 0000297
2012-02-01 09:01 wolin Status assigned => acknowledged
2012-02-01 09:09 wolin Relationship added child of 0000194
2012-02-02 10:51 wolin Note Added: 0000301
2012-02-06 17:27 wolin Note Added: 0000304
2012-02-06 17:27 wolin Note Added: 0000305
2012-02-06 17:27 wolin Status acknowledged => feedback
2012-04-04 17:45 wolin Note Added: 0000346
2012-04-06 13:54 wolin Note Added: 0000354
2013-03-20 18:03 wolin Note Added: 0000494
2013-03-20 18:03 wolin Status feedback => acknowledged
2013-06-14 10:56 wolin Note Added: 0000538
2013-06-14 10:56 wolin Status acknowledged => feedback
2013-07-18 09:15 wolin Note Added: 0000555
2013-07-26 15:59 wolin Note Added: 0000563
2013-07-26 16:25 wolin Note Added: 0000565
2013-07-26 16:25 wolin Status feedback => acknowledged
2013-09-09 17:17 wolin Note Added: 0000575
2013-09-09 17:17 wolin Status acknowledged => feedback
2014-04-08 12:38 hovanes Status feedback => closed