Meeting Time and Place

Tuesday, April 23, 2024, 1:15pm Hall D Counting House

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard

Agenda

Minutes

  • Reviewed minutes from last meeting
  • Translation from NX to Fluka were largely unsuccessful
  • Need to give x, y and z coordinates of shielding around the absorber to Pavel to rerun Fluka model (Keith H.)
  • Get Pavel magnet dimensions to rerun Fluka (Stephanie)
  • Magnet will be supported on same support as absorber/shielding
  • Discussed use of air casters to move the CPS assy around during installation and moving after commissioning
    • About $35K to procure system
    • It will give us much ore flexibility during assembly
    • Need to rent a portable compressor (200 SCFM) with 2" air lines
    • seemed to be acceptable plan, we will pursue this further
    • Concerns with radioactive dust (contamination)
    • Get with ES&H/RADCON to discuss mitigations
    • Will see if anyone else at the lab has used this or owns a system - no go
  • Discussed Project Gant chart being developed for the entire KLONG project -
    • will send a preliminary out soon (Tim)
    • Will include schedule and manpower needs
    • Keith H. will most likely have less time in the near future to work on KLONG
  • Brazing test planned for absorber
    • 8" Z length 1/2 of the absorber
    • three 3/8" supply and return per half
    • tubes brazed into section with no water exposed joints inside shielding
  • Magnet
    • Still need to determine if less expensive resin can be used
    • All water exposed joints will be outside shielding

Action Items