CPP and NPP Run Conditions
From GlueXWiki
- CPP and NPP Run Conditions
- Electron beam energy expected = 11.57 GeV based on the planned Experimental Schedule
- Microscope will cover the range of [0.391-0.514] of the beam energy or [4.52-5.95 GeV]
- Hall D solenoid will operate at its nominal field of 1350 A.
- Use the 750 um PS converter to collect sufficient PS triggers at low rate.
- Pair Spectrometer magnet will be scaled down by 6/9 = 0.67 of its nominal field (569.4 A = 0.67x849.9 A)
Activity | Duration (PAC Days) | Duration (hours) | Current | Target | Collimator | Radiator | Contact | Comment |
---|---|---|---|---|---|---|---|---|
Full target (Production) | 20 | 960 | 27 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Alternate 45, 45, 135, 135 deg diamond configuration (240 M events each) with amorphous data (60 M events) | |
TOF, CTOF, CDC HV Scans | 0.2 | 10 | 27 nA | - | 3.4 mm | AMO (1x10-4) | Beni, Naomi, Mark | Need time to assess data before updating settings. FCAL/BCAL trigger |
Empty Target | 1.5? | 72 | 50 nA | - | 3.4 mm | JD70-103 or JD70-107 | Rory, Ilya, Andrew | Take data at full-target current for normalization |
Diamond Alignment | 0.5? | 24 | 20 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 and JD70-107 | Hovanes | |
Trigger Commissioning | 1? | 48 | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Sasha | |
Lead Shield Alignment | 0.2 | 10 | 30-100 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Ilya | |
Beam Energy Calibration | 0.1? | 5 | 100 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Alexandre | Collimator Blocking for 5 min, periodically |
Straight Track (Solenoid off) | 0.5? | 24 | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Simon, Lubomir | Ramping magnet takes about a shift. |
PS magnet at GlueX nominal current | 0.1? | 5 | 27 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 or JD70-107 | Sasha? | |
TAC Runs | 1.5? | 72 | <2 nA | - | 3.4 mm | AMO (2x10-5) | Sasha | |
All Non-production total | 5.6 | 269 | - | - | - | - | - |
Contents
Preparations and Schedule
Draft Commissioning Steps
- Set Solenoid (standard GlueX) and PS magnet to CPP values (CPP = 2/3 * nominal GlueX).
- Setup photon beam operation at 50 nA.
- Check microscope and hodoscope operation in new configuration
- Align diamond to 6 GeV coherent edge
- Check rates in microscope in new position
- Harp scans and check photon beam on collimator
- Check radiation and backgrounds rates in Hall D with Pb target
- Check rates and beam stability at 30 nA
- Check currents and hit distributions in the MWPCs
- Preliminary trigger setup to be used during initial checks
- Complete a HV scan for the TOF, CTOF and CDC. Adjust voltages accordingly, especially those of the TOF in advance of trigger studies.
- Take data for adjustment of the FCAL PMT gains.
- Take data for Sean's Detector Checkout
- Compare empty vs full target rates
- Media:full_empty_running.pdf Determination of optimal running point
- GlueX-doc-5651 Initial Analysis
- Log Entry 4005395 Toy MC to study empty statistics
- Adjustable Pb absorber (upstream of muon detector)
- Proposal (Ilya)
- Commission trigger
- Charged Trigger (TOF)
- Neutral Trigger (FCAL/BCAL)
- Calibration triggers (CTOF, random, PS)
- Compare empty/full trigger rates
- Production
- Full target
- Empty target, fraction determined during commissioning.
- Special Runs during Production
- Beam energy calibration (Short, possible daily runs)
- Regular short runs in raw mode
- Take a TAC run close to start and one at end of run.
- PS: Take data at the nominal GlueX setting for reference.
- Straight track data (solenoid off)
Non-production activities remaining (Jul 27)
- Second TAC run (> 7 days from end of run)
- Take a current rate scan on full target later in the run to investigate any rate dependent effects. Do we want to do this? When?
- PS magnet at nominal current?
Decommissioning / Deinstallation
- The Pb target will be secured upon completion of the experiment. It will be stored either in a safe in the hall if it is activated, or the safe in Hall D conference room if not.
- The Pb frame shield will be surveyed while the first stage is still up on the platform
- After uncabling of the MWPCs, the chamber cables will be stored along with the chambers in the EEL.
- The steel absorbers will be stored inside to prevent corrosion, likely in the Test Lab.
- The CTOF scintillators will be stored in the EEL along with the MWPCs. That gets them out of the hall radiation environment and makes them accessible even if Hall D is closed.