Coil Test Weekly Meeting 11-Mar-2010

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 11-Mar-2010 9:45am ARC 428


Agenda

  • Networking, computers and accounts for coil test - Elliott
  • Safety review meeting, ODH analysis,OSP, etc. - Elliott, Josh
    • OSP committee: Bob May, Paul Collins, Todd Kujawa, maybe others
    • need to identify "design authorities" for every aspect of OSP review
    • ODH will be handled by Mat Wright, signed by Dana Arenius
    • do we need weld inspections?
    • can we avoid any analysis of the PLC program?
    • need list of all previous reviews
    • will we need any external reviews?
  • P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
  • Status of PLC programming - Mark W
  • A-B software licenses, HMI and web programming - Elliott, Yi
  • What PLC display pages are needed (HMI and web) - Josh
  • Wiring progress in F117 - Scot
  • How will we test PLC program - Mark W, Scot, Mark S
  • Installation in current and QWeak areas - Tom
  • Tying into existing vent piping system - Tom
  • Status of miscellaneous parts orders - George
  • Coil 1 repair status - George
  • Coil 2 repair status - George
  • Coil 3 progress at IUCF - George
  • Coil 4 controls wiring replacement - George
  • 5 G contours - George
  • Coil Test Top To-Do items