Coil Test Weekly Meeting 11Feb-2010

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 11-Feb-2010 9:45 am ARC 428


Agenda

  • Supplying EPICS values to PLC via Linux computer - Elliott
  • Behavior of power supply after brief power loss and reestablishing coil current - Elliott
  • What goes into fourth controls rack - Scot
  • EWEB module - Elliott
  • Report on safety meeting, final P&I diagram, machine protection, failure scenarios - Josh
  • Status of PLC programming - Mark W
  • Wiring progress in F117 - Scot
  • Status of items on George's punch list - George
  • Do we want to tie into existing vent piping system - Mark S, Scot
  • What PLC display pages do we want, and what should be archived and how often - George
    • main pages, fault pages, trends, etc.
  • Coil 1 cryostat testing status - George
  • Coil 1 status - George
  • Coil 2 cost and schedule - George
  • Coil 3 statement of work, visit and IUCF contract - George, Tom
  • Coil 4 controls wiring replacement - George
  • Shipping rails and transportainer from IUCF - Chuck
  • Backup computer - Elliott
  • Safety reviews, formal process - George, Elliott
  • 5 G contours - George
  • Coil Test Top To-Do items