Coil Test Weekly Meeting 25-Mar-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 25-Mar-2010 9:45am ARC 428
Agenda
- Safety review and progress towards getting OSP and COO - Elliott, Josh
- Discussion with Dennis Skopik
- OSP writing assignments
- outside "subject matter experts"
- Progress concerning EWEB module, HMI programming, UPS, terminal server, etc. - Elliott, Yi
- P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
- Status of PLC programming - Mark W
- Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
- What PLC display pages are needed (HMI and web) - Josh
- Wiring progress in F117 - Scot
- Installation progress - Tom
- Tying into existing vent piping system - Tom
- Status of all parts orders - George
- Coil 1 repair status - George
- Coil 2 repair status - George
- Coil 3 progress at IUCF - George
- Coil 4 controls wiring replacement - George
- 5 G contours - George