Coil Test Weekly Meeting 3-Dec-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
Note new meeting day
- Fri 3-Dec-2010 9:30 am ARC 428
Agenda
- Do we want to install a second quench detector - Mark, Elliott
- Cryogenic operations experience - All
- vapor-cooled lead blockage
- document our experience
- additions to HMI and EWEB pages
- Status of preparation for powered operations - All
- shunt for fast and slow dump
- fast DAQ
- sweep, signage, etc.
- UPS lifetime test
- alarm system
- paging system and guard shack
- HMI status, archives, etc.
- second HMI computer
- Status of 230 V UPS on Danfysik control boards, main switch - Elliott
- Elog - Elliott
- automatic entries
- Coil repair status - George
- coil 3 at IUCO
- coil 2 winding supports
- plans for coil 4
- PI Responsibilities during test - Jonathan
- Low power magnet testing 5A, 50A,100A - Elliott
- High power magnet testing 100-1500A - Elliott
- Identify possible turn to turn shorts during ramping - Eugene
- Assess Heim column centering in coil - George
- Assess Axial column forces - George
- Estimate LN2 and He heat leak - Jonathan
- Assess LN2 and LHe thermal siphons - Jonathan
- Preparations for testing next coil - George, Scot, Elliott
- ship coil 3 to JLab
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- quench detector
- connectors
- what else might be useful?