Agenda
- Fourth controls rack - Scot, Elliott
- EWEB and other A-B modules - Elliott
- Safety meeting - Josh
- Updated P&I diagram including machine protection systems - Josh
- Final narrative including cryo, power, safety, machine protection, fault diagnosis - George
- Status of PLC programming - Mark W
- Status of controls drawings and wiring lists - Scot
- Wiring progress in F117 - Scot
- Status of items on George's punch list - George
- GN2 vent piping system tie-in - Mark S
- When do we start installing things in Test Lab - Tom
- delivery dates of platform stand, cryo can, IUCF items, etc.
- What PLC display pages do we want, and what should be archived and how often - George
- main pages, fault pages, trends, etc.
- FastTrack schedule status - George, Chuck
- Coil 1 cryostat testing status - George
- Coil 1 status - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Arrange for electrical work in Test Lab - Tom
- Arrange for telecom in Test Lab - Elliott
- Arrange for networking in Test Lab - Elliott
- QWeak area, bigger door in F117 - Tom
- Locating computer in SRF control room - Elliott
- Backup computer - Elliott
- Safety reviews: when to start formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items