Coil Test Weekly Meeting 5-Nov-2009

From GlueXWiki
Jump to: navigation, search

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 5-Nov-2009 9:45 am ARC 428


Agenda

  • QWeak area: when can we get in, how will we use it - Tom
  • Si diode readout - Elliott
  • Preparation for 18-Nov magnet review - All
    • n.b. I will be out of town that week
  • Ordering cryo can - George
  • Cryo and electrical interface, relief system - Josh, George
  • Cryogenic wire and wire insulation - Scot, George
  • Coil 1 testing and wire replacement - George
  • Coil 2 cost/schedule review, etc. - George
  • Coil 3 statement of work, visit and IUCF contract - George, Tom
  • Coil 4 controls wiring replacement - George
  • P&I, controls drawings, narrative - George, Mark S, Mark W
  • Construction/installation sequence drawings - George, Chuck
  • Ordering platform - George
  • Shipping jack stands and rails from IUCF - Tom
  • PLC programming and testing - Mark W
    • we have approximately one man-week of Steve Lassiter's time
    • how to use it wisely?
  • Ordering remaining controls instrumentation and components - Scot
  • Controls racks in F117: when do we begin installation of controls instrumentation - Mark S, Scot
  • FastTrack update strategy - George
  • Review "Top To-Do" items - Elliott
  • Review of recent progress, identify action items - All