Coil Test Weekly Meeting 8-Apr-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
Note Earlier Start Time
- Thu 8-Apr-2010 9:30am ARC 428
Agenda
- Wiring completion date and moving into Test Lab - all
- What additional computers are needed? - all
- Analog output module to control new valve - Josh, Mark S, Mark W, Scot, Elliott
- Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
- OSP writing assignments and subject matter experts
- HMI and EWEB programming, UPS, terminal server, etc. - Yi, Elliott
- EPICS connection to PLC - Elliott, Wesley
- P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
- Status of PLC programming - Mark W
- RS232 Point I/O module restrictions
- Lakeshore calibrations
- Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
- What PLC display pages are needed (HMI and web) - Josh
- Wiring progress in F117 - Scot
- Parts orders, installation progress - George
- Coil 1 repair status - George
- Coil 2 repair status - George
- Coil 3 progress at IUCF - George
- Coil 4 controls wiring replacement - George