Construction schedule milestones

From GlueXWiki
Jump to: navigation, search

Active Collimator

  • 01/05/2012 - 07/10/2012 - Procument Active Collimator Components
  • 07/11/2012 - 01/23/2013 - Assemble Active Collimator
  • 07/11/2012 - 12/14/2012 - Program and Test Collimator Table
  • 01/23/2013 - 04/24/2013 - Test Active Collimator

Tagger Microscope

  • 10/03/2011 - 04/13/2012 - Procument Fibers for Microscope ($11,905)
  • 12/02/2011 - 06/14/2012 - Procument SiPMs for Microscope ($136,060)
  • 10/03/2011 - 05/25/2012 - Design and Layout Preamplifier Board
  • 06/15/2012 - 05/03/2013 - Fabricate Counters Microscope ($26,470 labor)
  • 10/01/2012 - 15/03/2013 - Manufacture Base/Preamplifier Board ($24,365)

Fixed Array Hodoscope

  • 01/05/2012 - 07/10/2012 - Procument Scintillator/Light Guide for Fixed Array ($7,871)
  • 01/05/2012 - 07/10/2012 - Procument PMTs for Fixed Array ($51,589)
  • 01/05/2012 - 07/10/2012 - Procument Dividers for Fixed Array ($30,636)
  • 03/08/2012 - 06/08/2012 - Fabricate and Test Fixed Array Counter