Modified Goal

  • Statistics Similar to Spring 2017 would be sufficient for Fall 2018
  • 2016 Golden Period: 7 billion triggers
  • Spring 2017 Running: 47 billion triggers
  • Spring 2018 Running: 145 billion triggers

Original Plan

  • August 22 to October 28 9.5 Weeks of Running Complete GlueX Phase I
  • October 29 to November 19 3 Weeks Installation of CompCal and DIRC
  • November 19 to December 19 4 Weeks CompCal and DIRC Commissioning

Modified Plan at Collaboration Meeting

  • September 28 to November 10 6 Weeks GlueX Phase I
  • November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible)
  • November 26 to December 19 3 Weeks CompCal Commissioning

Where do we stand?

  • There are 45 days in the 9/28 to 11/10 period.
  • We have run 11 days and collected 13 billion triggers
  • We have 34 days remaining, would expect an additional 40 billion triggers
  • We now expect about 53 billion triggers
  • Spring 2017: 47 billion
  • Spring 2018: 145 billion
  • Fall 2018: 53 billion (est)

Discussion

  • The machine will run 11.6 GeV until 26 November, potentially 16 more days, or 19 billion more triggers.
  • Fall 2018 could be ~72 billion triggers (1/2 of Spring 2018).
  • Such a change means CompCal Commissioning is cut to 1 week?