For the third coil
From GlueXWiki
To-do list
- Wiring
- rewire for coil 3 subcoils - done 25-Apr-2011
- 20 kOhm protection resistors for coil taps if needed for quench detector balancing - not needed 7-Apr-2011
- document trip chains
- label circuit breakers
- Danfysik power supply
- add new readout channels - done 25-apr-2011
- fix broken transistor - done 20-Apr-2011
- commission fault sequencer
- fix slow dump
- understand ramp-down mechanism
- understand varying fast dump time constant - possibly understood 8-Apr-2011, needs verification
- choose ground fault detection mechanism
- cover holes in cabinet - done 8-Apr-2011
- Danfysik quench detector
- install bias pot on remaining three channels - done 7-Apr-2011
- implement divider circuit upstream of QD to eliminate effect of coil imbalances - not needed 7-Apr-2011
- install trip test points
- Instrumentation
- ensure all devices on clean power with good grounds - done 8-apr-2011
- check out Newport controllers, flow switch, replace if needed - done 25-apr-2011
- implement system to isolate fault detectors and determine time sequence of trips - postponed 8-Apr-2011
- understand spikes on shunt Newport - may never understand them...
- understand effect of B field on all sensors, move devices if needed - devices moved 8-Apr-2011
- monitor circuit breakers?
- NI USB device - replaced by VME DAQ system 7-Apr-2011
- rework Zener/divider box, needs to be fully bipolar
- eliminate noise
- VME-based fast DAQ
- get hardware, test in lab - done 7-Apr-2011
- write software, test in lab - done 25-Apr-2011
- connect to apparatus - done 25-Apr-2011
- real-time graphics
- A-B HMI improvements
- upgrade to 100 screen license - done 6-May-2011
- implement fault sequence screens if system implemented - not implemented 8-Apr-2011
- A-B PLC program improvements
- mods for new coil configuration - done 25-Apr-2011
- EPICS
- new channels
- EWEB screens
- update for latest tags and drawings
- Auxiliary tests
- requirements, setup for aux tests - done 12-May-2011
- Reenable cron job
- when cooldown commences, end when warmed up - done 1-May-2011
For the hall
- note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
- need travelers for coil installation.
- should we install a UPS on the Danfysik contactor and control boards?
- should we install a second contactor in the Danfysik power supply?
- do we need additional valves, check valves, bypasses, whatever?
- do we need Dataforth voltage attenuators on coil tap channels?
- do we need active isolation of coil tap channels, etc?
- should we monitor all circuit breakers?
- should we monitor all relays?
- what is the effect of B field on sensors/relays? should some instrumentation be relocated?
- do we need new flow sensors, or should they be relocated?
- lock box for power supply key
- more ethernet power strips
- use custom ("add-on") instructions to simplify PLC code