Hodoscope Fabrication Readiness Review

From GlueXWiki
Jump to: navigation, search

Date and Time

1:00 pm, June 11, 2013, room F326

Video Connection information if needed

JLab Conference Room L102

  • ESNET and EVO session
  • Phone only if requested:
    • +1-866-740-1260 : US
    • access code: 3421244# (remember the "#"). Phone line by request only.

Participants

CUA

  • Franz Klein (Professor of Physics)

JLab reviewers

  • Fernando Barbosa (Hall D eletrical engineer)
  • Eugene Chudakov (Hall D group leader)
  • William Crahen (Hall D engineer)
  • Glenn Young (Associate Project Manager for Physics)
  • Mark Ito (Hall D Staff)
  • Bruce Lenzer (JLab ESH&Q)
  • Vladimir Popov (JLab, ESH)
  • Elton Smith (Hall D Staff)
  • Alexander Somov (Hall D Staff, SOTR)
  • Timothy Whitlatch (Hall D engineer)
  • Jarrod Fitzpatrick (CFO)

Topics/Issues that need discussion/resolution

Documents on the Hodoscope Construction

Meeting Agenda

  • 13:30 Project Overview
    • Scope of contract and current review
    • Status of construction
  • 14:00 Review construction procedures
    Work performed at CUA
    • Inspection (measurement) of scintillators and light guides. Parameters recording.
    • Wrapping materials
    • Wrapping procedures
    • Final inspection, storage, and shipping counters to JLab
    Work performed at JLab
    • Checking PMTs and electronics
    • Overview counter's mounting frame and procedures
    • Fixture to mount light guides on the support collar
    • Gluing PMTs to light guides (gluing fixture, joint inspection).
    • Mounting counters on the support frame (position and alignment checks)
    • Final counter fabrication (housing, connectors ...)
    • Final bench tests (HV, electronics)
    Installation of counter frames in the Hall
    • Installation procedures
    • Final Tests
  • Review Technical Documents
    • Construction Plan
    • Testing procedures
    • Quality Assurance Plans and Acceptance Test Plans
    • Documentation and Travelers
    • Personnel training
    • Schedule and Tracking
  • 15:00 Meeting with JLab Financial people.
    • Billing and Reporting
  • 15:30 Closeout
  • 15:40 Adjourn

Contract Related Documents

(use gluex account to access files)

Construction Plan

Quality Assurance and Acceptance Test Plan

Statement of Work

Personnel Training

Quality Assurance Checklist