July 15, 2022 Tech group meeting

From GlueXWiki
Jump to: navigation, search

Meeting Time and Place =

Friday July 15, 2022 10:30am TEDF 2504 and Teams

Agenda

  • Safety - chop saw? 480 vs 208 plug
  • Last day to submit PR for FY 22, Aug 19
  • CPP removal/Primex install gant chart O:\halld_engineering\Installation Schedules\MS Projects
    • Most likely delayed until Aug 17
  • Hall D current Tasks
    • FCAL Insert Module fabrication
      • 120 brass straps per week needed now?
      • matching mu metal to steel shields
      • cutting tool
      • Tent move to EEL 108
    • Tagger NMR issues
  • FCAL Insert Drawings - 98% complete
    • need cooling pipe to chiller assy
    • need dark room mod for electronic patch panels, need to complete 0200 final assy dwg
    • need installation drawing
    • insert plexiglass
    • Tungsten
    • Procurement plan developed and started J:\Hall D\FCAL insert
  • New Profiler install - not until August 17 - new plates arrived, need to add this to schedule
  • Controls
    • FDC chiller cooling water flow -
  • DIRC Bar Box DP sensor
  • General Maintenance
  • On Call -
  • ePAS Training and trial https://www.jlab.org/esh/epas

Action Items