July 29, 2022 Tech group meeting
From GlueXWiki
Meeting Time and Place =
Friday July 29, 2022 10:30am TEDF 2559 and Teams
Agenda
- Safety - Covid? High transmission?
- Last day to submit PR for FY 22, Aug 19
- NASA windtunnel tour
- CPP removal/Primex install gant chart O:\halld_engineering\Installation Schedules\MS Projects
- delayed until Aug 18, needs to be completed by Aug 26
- Hall D current Tasks
- FCAL Insert Module fabrication
- brass straps
- matching mu metal to steel shields - steel housings can be picked up from annealing Monday morning
- cutting tool
- Tent move to EEL 108 - move tables next week
- Tagger NMR issues
- FCAL Insert Module fabrication
- FCAL Insert Drawings - 98% complete
- need cooling pipe to chiller assy
- need dark room mod for electronic patch panels, need to complete 0200 final assy dwg
- need installation drawing
- insert plexiglass
- Tungsten
- Procurement plan developed and started J:\Hall D\FCAL insert
- Assemble FCAL2 step plates - arrived in ESB
- New Profiler install - not until August 18 - new plates arrived, added to schedule - may be delayed
- Controls
- solenoid ramp
- FDC chiller flow meter
- DIRC Bar Box DP sensor
- DIRC vacuum pump cooling water
- General Maintenance
- On Call -
- ePAS Training and trial https://www.jlab.org/esh/epas