Action Items from previous meetings

  1. Develop front and back views of jumper sheets. (Jack)
  2. Check into AC units based on Peltier coolers for SiPM production tests (Fernando)
  3. Review Fcal LED and controller monitoring boards (Fernando)
  4. Decide on size of overlap of voltage bins for the SiPMs (Yi and Jack)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
    • SiPMs assignment for new boards
  5. Mechanical assembly (Scot)
  6. Mechanical (Jim)
  7. Mechanical drawings (Chuck)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Chris)
  10. Light guide gluing setup

Minutes

Attending:Jack, Nick, Chris, Elton, Jim, Eugene

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
    • SiPMs assignment for new boards
    • Decided that a "random" distribution of SiPMs might be best for this set of boards.
  5. Mechanical (Jim)
    • Glue is in for RTD and Cooling tubes
    • Converting SiPM machined tray to molded part, which includes bosses
    • Joseph is putting together box for testing the readout.
    • Chiller: Check range of temperatures can cool SiPM in the range of 5 - 60 deg C. (The higher temperatures are needed for annealing the SiPMs)
  6. Temperature compensation (Jack)
    • Has code operational that can be used to determine overlaps between jumper settings. He will coordinate with Yi.
    • Also starting to develop the front and back views for jumper settings.
  7. Preamp-summing (Chris)
    • All 4000 populated U-boards are completed
    • Transition boards and thermistor boards (production) have been ordered
    • All HFL and UFL cables are on order and most are in but not all
    • The two readout boards are out to be populated, expected in about 10 days.
    • Thermal mats need to be ordered.
    • Cooling loops need to be brazed in.
    • 14-pin trim trio connectors are in, replacing the three previous connectors
    • The circuit board and micro-Dsub connector for the monitoring board needs to be made. Chris and Jim will discuss after the meeting.
  8. Light guide gluing setup
    • The vent hoods are being fabricated
    • Light guide production has been delayed due to a broken part in the milling machine. Light guides are now expected in a couple of weeks.