May 6, 2022 Tech group SAD meeting
From GlueXWiki
Meeting Time and Place =
Friday May 6, 2022 10:30am Hall D Counting House and Teams
Agenda
- Safety - collimator cave Active collimator access
- still no budget to buy FCAL2 stuff
- Accelerator schedule - HCO started
- Hall D SAD Tasks
- CPP INstall O:\halld_engineering\Installation Schedules
- Microscope move/Hodoscope - complete
- Moveable Lead absorber - Tim to Write procedure
- Target - installed-leak checked - re-survey needed - need drawings
- Gas - Scot/Chris
- Helium bag Installed installed
- PS Parasitic Detectors stages - low priority
- FCAL Insert Module fabrication
- 40 brass straps per week needed, maybe 60 now?
- matching mu metal to steel shields
- cutting tool
- Moving tent end of June to EEL 108
- Tagger NMR repair and HCO - Scot
- Tagger controls/network switch UPS
- Target/Goni Turbo repair - Keith
- Move active collimator to 3.4mm hole
- Goniometer light replace
- Downstream vacuum pipe install
- Add casters to Microscope stand
- Rebuild Goni diaphragm pump
- CPP INstall O:\halld_engineering\Installation Schedules
- TEDF work area move in June to test lab high bay
- FCAL Insert Drawings - almost complete
- need cooling pipe to chiller assy
- need dark room mod for eelectronic patch panels
- need installation drawing
- New Profiler install
- New 3x3 CCAL for TAC Media:CPP_TAC.pdf
- Tagger Radiator Mod Media:Fork_mod.pdf
- Controls
- FDC chiller cooling water flow -
- FDC start up procedure with set point error - test again?
- General Maintenance
- On Call - Bobby
- ePAS Training and trial https://www.jlab.org/esh/epas
Action Items
- Prepare for HCO