Minutes 060913
From GlueXWiki
Attendees: Alex, Matt, Eric (Indiana), Elton, David, Elliott, Dan Carman, Blake, Rafael, Simon (JLab), Franz, Dan Sober (CU), George, Garth, Yianna, Zisis (Regina)
- Business Arising
- Action Items: See updated list below.
- Hall-B
- Electronics and Cabling: The upper half of the tagger cabling is done; the lower half is still apart for planned installations of new shields; everything should be ready by Friday. EPICS problem is solved. Network cabling is not done. We can survive as is but with reduced bandwidth. We now have capability to view 6 scope channels in the counting house.
- DAQ/online: The tagger creates have been read successfully (phew!).
- PMTs/Cosmics: Plots of the PMT gains have been circulated by email. They show the Burle and XP2020 PMTs grouped seperately, with the latter having lower gain; this is opposite to expectations. Perhaps this is caused by the bases used; all bases read the anode and the quantum efficiency of both types of PMTs is approximately the same. The South PMTs look ok, but there is a systematic problem with the North ones. Ideas to check were presence of a magnetic field, zero suppression in the ADC, ADC gates, grounding issues, etc. The cabling between North and South will be swaped to further investigate this.
- Run Plan: Zisis continues to update the Run Plan. The key issues discusssed today were:
- Blake will coordinate the cosmics energy calibration to that expected from photons in all situations. The former is based on 4-5 MeV energy deposit per cell, whereas the latter ranges from < 1MeV on outer cells, to 60 MeV for a steep angle in a central cell. We appear to have adequate dynamic range for this.
- The Hall will be locked in the evenings next week. We should attempt to take advantage of any beam.
- Monte Carlo:
- Rafael will simulate the effect of 0.5-3mm lead pre-radiator in front of the BCAL.
- Any other business
- It was suggested to have meetings at JLab to review progress at the end of each day.
- Doug Tilles will be trained in cart operation.
- Franz will work on the tagger commissioning procedure.
- We will (tentatively) schedule a Hall-B walk through on September 22.
Action Items
- BPM, Veto: Slow control cables and stand construction pending.
- Light Leak: Light leak test pending in alcove.
- Tagger, Trigger, Cables: The fast core cable is pending.
- Data storage/Silo Request: David and Zisis will deal with this offline.
- Online Macros/MC Data steam/MC Validation & Binning: In progress.
- Run Plan: Produce table with positions, angles, beam current, pre-radiator runs.
- Hall-B Walk Through: Elliott will schedule this with H-B folks for Sept. 22.