Run Coordination Meetings: Fall 2015 min10 02

From GlueXWiki
Jump to: navigation, search

Meeting minutes: October 02, 2015

Present:Alex B., Alexandre D., David L., Curtis M., Matt S., Elton S., Alex. S.

  • When to start readiness meetings? HCO?. We can start with a weekly 8:45 meeting, after the collaboration meeting. HCO can start beginning of November.
  • We do not expect to have beam before after Thanksgiving before starting operations involving Hall D. There are 4 scenarios:
    • Miracle scenario: everything is proceeding without any hitch. Then the beam could be ready before Thanksgiving.
    • Realistic good scenario: everything is proceeding as expected. Beam comes around Thanksgiving. We have the 10 first days busy with FFb commissioning. The remaining few days of swing and night shifts will be for Hall D commissioning
    • Realistic bad scenario: the 12 GeV goal is reached near mid-December. There will be no beam in the tagger or in Hall D. FFB commissioning is postponed to Spring 16.
    • Really bad scenario: the 12 GeV goal cannot reached. Accelerator would switch to Hall operation at lower energy. Depending on when accelerator decides that 12 GeV cannot reached for Fall, we may get beam availability before Thanksgiving.
  • Run conditions:
    • Target: Cryotarget will not be cooled down. We should install the 10mm disk of CH2 (HDPE, high density polyethylene) on the ST nose. Tim W. has been contacted about this.
    • Hardware and softwares for the fast feedback commissioning are close to be ready. They should be ready for the Fall run with plenty of safetey margin.
    • Can all/most of the solenoid work be done in Controlled Access?
    • Once the FFB commissioning start, there will still a priori be no need to man the counting room until radiators need to be inserted (end of the commissioning involving the Active Collimator). Gain changes for the Active Collimator will be handled by the accelerator. Richard J. and Alex B. to provide Trent A. and Brian B with a procedure. However, the FFB tests will likely be followed by a few hours of beam for Hall D use. The counting room will need to be staffed then. Probably, we will need to have night active shifts and standby day and swing shifts.
  • Schedule, list of tasks:
    • We do not expect to have beam until after Thanksgiving.
    • Before starting operations involving Hall D:
      • Hot Checkout update
      • 12 GeV beam must be established.
      • Probably, high current run (100μA) will then occur (beam in Hall A) to test cavity loading.
    • FFB commissioning: The test will start at 1μA, and possibly 3μA. RadCon has been notified. No radiator will be in place but, due to the nature of the commissioning, beam scrapping will occur. ⇒ We must be sure that the Ion Chambers are properly calibrated and their threshold properly set before to start the commissioning. Since the beam will be shut down quickly, no special additional shielding or precautions need to be taken for the tagger electronic.
    • Beam tuning for FFB commissioning will start in the evening. Then a few hours of FFB will follow. The rest of the night will be available for other Hall D commissioning tasks.
    • FFB commissioning will be concluded by low current (5nA) nA-BPM commissioning.
    • Beam line FOPT. About 2h of data. Data for beam energy stability study will be gathered at the same time.
    • Tagger detector commissioning (parasitic to FFB work). Alex. B. and Richard J. provided a test plan.
    • Trigger tests
    • DAQ work. The goal is to optimize DAQ performance and find DAQ rate bottlenecks: data rate, trigger rate, live time. Several parameters have to be defined for every DAQ components independently: detectors readout (for FDC,CDC,FCAL,BCAL,...), event builder, data concentrators, event recorder, to find the slowest. Optimization includes different triggers and beam current. FDC/CDC will be needed for about 30min with a 50-100nA current. In a nutshell:
      • The detectors will be running the same hardware (no new fiber bundles for Fall15) and software as the previous run.
      • Before the start of the run, there may be a 2h work in the tagger Hall If some microscope control boards need to be replaced with the now available spares. (Alex B.)
      • Bias voltage study with 2 voltage settings. About 2×40min of data taking if we get about 1kHz PS trigger rate. This can be done parasitically to the FFB work.
      • Collect about 4h of data (should provide 1M events).
      • Possibly: fiber alignment checks (Alex. B to let us know if it is necessary and how long it would take)
    • Trigger tests at high current (μA): Alex S.
    • Lubomir P. and Sergei F.: transition radiation studies.