Run Planning Meeting Notes, Dec 12-Dec 20, 2019

From GlueXWiki
Jump to: navigation, search

Thursday, Dec 12 at 08:45

  1. Last 24h:
  2. Issue:
    • DAQ crash
      • DAQ issues (of manifest variety)
    • DIRC reference signal found in the stand alone configuration
    • Alarms for FDC HV
    • TAGM translation table
    • Data corruption issue in the beginning of the run.
    • rcdb event number issue.
  3. Task for today
    • Setting up high current test (Sasha)
    • CPP test crash (Dave)
  4. Plan for later

Friday, Dec 13 at 08:45

  1. Last 24h:
    • DIRC Gem data beam center configuration collected additional 5M trigger (6m triggers in total).
    • The CPP test (1 hour) run was completed
    • Overnight collected ~3 hours of DIRC commissioning data.
      • Diamond 0/90 Para/Perp & AMO at 150nA current, coherent peak at 8.6 GeV
    • 30 mins Raw mode data taken:
  2. Issues:
  3. Task for today
    • Hall Work
      • Relocate GEM/TRD
      • Installing additional flash module (Sasha)
    • Setting up high current test? (Sasha)
    • TOF: Beni
    • Profiler & FCal prototype: Ashark & Vlad
    • Low current ~3nA run (1 hour)? (Sasha)
  4. Plan for later


Monday, Dec 16 at 08:45

  1. Weekend running:
    • DIRC Gem data beam left configuration collected additional 6M trigger.
    • High rate trigger test completed
      • Bottle neck: DIRC at 250-300 nA.
      • Sasha is preparing a special trigger configuration
    • DIRC commissioning data:
    • Nominal configuration (Moroc threshold=100)~3B triggers
    • Moroc threshold=50 ~ 2B trigger (this weekend)
  2. Issues
  3. Task for today
    • Hall Work
      • Relocate GEM/TRD to beam right position
      • Installing additional flash module (Sasha)
  4. Plan for later

Tuesday, Dec 17 at 08:45

  1. Weekend running:
  2. Issues
  3. Task for today
    • DIRC HV channel swap
    • 30 min Raw mode data for the flash electronics debugging
    • TPOL firmware debugging
  4. Plan for later

Wednesday, Dec 18 at 08:45

  1. Past 24 hours:
  2. Issues
  3. Task for today
    • Completing setting up the high current test
  4. Plan for later