Run Planning Meeting Notes, Mar 19-Mar 28, 2018
From GlueXWiki
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Sunday, March 25 @ 10:00am
- Accelerator Status
- No significant progress on increasing total beam power since yesterday
- Started setting up Hall-B and Hall-D beams on Owl last night
- Will work on establishing Hall-D and Hall-B beams today
- RF expert is on site, but may not have anything new to try. May cause some loss in beam stability
- Likely to go back to working on power issue on Monday when full compliment of experts available.
- Beam likely to be very unstable for us then. Will know more Monday morning.
- Beam Authorization
- Run Plan
- Restablish Photon beam
- PS High Rate Check
- CDC Background Studies (Lubomir et al.)
- Converter thickness study (Alex S.)
- SSP Study (Alex S.)
- Production running
- Time Chart
- Reports
- Safety Issues
Monday, March 19 @ 8:45am
- Notes from the previous 48 hours:
- 8:00am MCC meeting report:
- transformers
- 2nd Transformer installed and powered up Saturday
- Work to restore cryo operation underway
- Halls asked to man counting house 24/7 starting Fri. 3/23
- Beam restoration over weekend with Physics expected to start Wed. 3/28
- transformers
- Solenoid ramped down
- Hall D in restricted access, tagger hall
- 8:00am MCC meeting report:
- Reports:
- AOB