Run Planning Meeting Notes, March 1 - March 8, 2023

From GlueXWiki
Jump to: navigation, search

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Wednesday March 8

Past 24 hours

  • More HI running, one run completed with tin foil, 25% through the program.
  • Continued work on BCAL prototype
  • Restoration of beam (to all 4 halls) - production
  • loss of beam after midnight - restored
  • Opted to do a harp scan as production resumed. (Been a while)

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

Plans

  • High Current Testing- IP
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Tuesday March 7

Past 24 hours

  • Begin of high intensity tests
  • Maintenance day part 5
  • Calorimeter Installation
  • Various hall accesses and repairs
  • Huge problems in late swing early owl with TAGH,Magnet
  • overnight production

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

Alarms During Maintenance

Plans

  • High Current Testing- IP
  • Anticipated MCC downtime: Hall Accesses? "Part 6"
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)
  • almost time for a harp scan?

Monday March 6

Past 24 hours

  • Production for most of day
  • RF Cavity trip (early swing)

Shift Reports

Early Riser Day Swing Owl

Reports

TAC run report(Sasha)

Issues

  • FCAL Lockups as usual
  • DIRC ROC alarm self healed when restarting DAQ (I happened to be in counting room)

Plans

  • Monday: High Intensity Running - IP
  • Cycle TAGH crate(need RadCon approval) - done
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Sunday March 5

Past 24 hours

  • Downtime part 4
  • TAC prep and run
  • Resume production

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Saturday March 4

Past 24 hours

  • Justin went into Hall to fix DIRC comm issue, looks good
  • Production running starting with AMO then on to the cycle. Offering catch-up of 80M events 45/135 PERP with new AMO reference hopefully rescaling Coherent Peak

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

  • DAQ had failure with some ROCs, needed work from Sasha and Sergey, completed by Sasha late Swing
  • Coherent Edge (Phoebe)
  • TAGH Crate [8] [9]

Plans

  • TAC Run (Sasha/Alexandre)
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Friday March 3

Past 24 hours

  • RadCon surveyed the detector prototype and it has been removed
  • ACC downtimes: 2L25 solenoid, BLM trips, 1L09 HV
  • Harp scan in Swing. The fits are "OK" though there have probably been better
  • Richard Jones does Normalization run using AMO with only Row 4 of TAGM to further the study.
  • OWL: resume production

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

  • Administrative: Error Connecting to VNC Suite - port 33 somewhat got killed. use 5901 or 5902 - part of it is my fault, due to remembering the wrong password...
  • DIRC alarms becoming more frequent [10] [11] [12] [13]
  • One FCAL lockup reported OWL shift

Plans

  • TAC Run (Sasha/Alexandre)
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Thursday March 2

Past 24 hours

  • MCC "Maintenance Day"
  • TAGM diagnosis, row checks
  • Production runs (Late MCC Swing and Owl)
  • After separate ACC issue beam came back 22:05 or so. Thought we were not reaching Richard so I gave him a call at 22:30 just to make sure. Call is successful and Richard goes ahead and does studies on the TagM gains

Shift Reports

Early Riser Day Swing Owl

Reports

Issues

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)
  • Sasha left segments of detector prototype for RadCon survey on Survey Table. He looks to ask the likes of Scot for guidance as RadCon will have to come when beam is down for a sustained period time.
  • Will we need a harp scan? MCC took away beam quite a while yesterday (nearly 14 hours before we got beam back)