Sep 22, 2011 SiPM Electrical and Cooling
From GlueXWiki
Action Items from previous meetings
- Carl to check instability of LED (as a possible contributor to sensor output changes) (Carl)
- Bias/temperature compensation review: Tentatively set for Oct 13 because Fernando will be out of the country till October and October 6 is the collaboration meeting.
- Fernando to provide dxf file to Jim, who has had trouble reading his stp files.
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM testing (everyone)
- Light source / optics
- Electronic boards
- Cabling
- Cooling plate
- Other?
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Geometry (Elton)
- Temperature compensation (Jack)
- Preamp-summing (Fernando)
- Granularity (Elton)
Minutes
Attending: Jack, Chris, Chuck, Jim, Ivan, Elton, Carl, Yi
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM testing
- Two samples have been tested, one from the beginning of the run and one from the end. They also have different operating voltages. No differences compared to first article
- Jack and Carl will review Hamamatsu data sheets, pick out another couple of samples to check against specs.
- Light source / optics
- all components in hand and moving to EEL 126
- Electronic boards
- Connector boards for cabling done, but need iteration due to flipped connector
- Question about grounding of 4 preamp boards. Jack suggested to use a common ground. Chris will go forward with this.
- Cabling
- Cables are in
- Cooling plate
- Iteration with Chris on the location of through holes, which has been resolved. Cooling plate will go to shop tomorrow.
- Other?
- Mechanical (Jim)
- Location of holes in plate have been iterated with Chris and drawings can now be made.
- Mechanical drawings (Chuck)
- Many drawings complete. Remaining drawings have been waiting final details but can now proceed.
- Geometry (Elton)
- Temperature compensation (Jack)
- Reviewing components. In particular the connector for the thermistor has not finalized. Discussion brought up the possibility of adding a thin PC board and a coax cable. This option will be checked further.
- Need to check HV rating of coax cable. Needs to hold at least 80 V.
- Jack has found that special runs for thermistor with better tolerance can be made at nominal cost. This will be useful.
- Preamp-summing (Fernando)
- Granularity (Elton)
- SiPM timing tests (Ivan)
- All equipment is in place, except for the generator, which is expected by mid Oct.
- Will start working on the DAQ next week
- When generator arrives, he will start testing timing using 2 LEDs.