Difference between revisions of "October 21, 2021 CPP Design Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 11: | Line 11: | ||
** Lead absorbers - out for bid | ** Lead absorbers - out for bid | ||
** All assembly hardware wither here or due in by December | ** All assembly hardware wither here or due in by December | ||
− | |||
− | |||
− | |||
− | |||
− | |||
** Stand All parts here -assembled in the TEDF High bay [[image:cpp_stand_5.jpg|thumb]] | ** Stand All parts here -assembled in the TEDF High bay [[image:cpp_stand_5.jpg|thumb]] | ||
** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ||
− | ** | + | * Installation/assy 3D Model and dwgs |
− | *** | + | ** DS Chamber orientation? |
− | *** | + | ** Scintillator orientation? |
+ | ** assembly components - drawings released | ||
+ | ** Installation drawings in review | ||
+ | * Target Design in work | ||
+ | |||
* Things to work out | * Things to work out | ||
** Gas system, manifold/bubblers (Beni has some) | ** Gas system, manifold/bubblers (Beni has some) |
Revision as of 14:31, 21 October 2021
Meeting Time and Place
Thursday October 21, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/September_09,_2021_CPP_Design_Meeting
- Testing status - Beni/Elton
- Design/Fab/Procurement status
- Lead absorbers - out for bid
- All assembly hardware wither here or due in by December
- Stand All parts here -assembled in the TEDF High bay
- Steel - all received
- Installation/assy 3D Model and dwgs
- DS Chamber orientation?
- Scintillator orientation?
- assembly components - drawings released
- Installation drawings in review
- Target Design in work
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage