Difference between revisions of "JEF meeting, March 31, 2023"
From GlueXWiki
(→Agenda) |
|||
Line 18: | Line 18: | ||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
− | ** Fabricated modules: <span style="color:#FF0000"> Total 1482 </span> | + | ** Fabricated modules: <span style="color:#FF0000"> Total 1482 </span> |
− | **: Currently available for fabrication: 0 | + | **: Currently available for fabrication: 0 (modules will be available during next week) |
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 + 3 SICCAS] --> | <!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 + 3 SICCAS] --> | ||
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 834 CRYTUR], available: 1 --> | <!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 834 CRYTUR], available: 1 --> |
Revision as of 09:14, 31 March 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Available crystals:
- 1450 (modules)
- 32 (ready for fabrication)
- 40 (installed on CCAL) available on March 20
- (some CCAL crystals from the inner part will not be used for the FCAL2)
- 95 expect to receive from CRYTUR in May [1] Expect to start shipping crystals in the 2nd week of April.
- Total 1617
- Disassemble the CCAL prototype
- George (DSG group) is unwrapping CCAL modules and removing LMS caps. He'll also work on preshaping ESR reflectors (100 pcs) for CRYTUR.
- Mindy (DSG group) solder wires to sockets (while waiting for crystals). She will continue with crystal wrapping during next week.
- Available crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1482
- Currently available for fabrication: 0 (modules will be available during next week)
- Fabricated modules: Total 1482
- Testing of PMT dividers -- Sasha / Arshak
- FCAL2 modules with dividers installed on the CCAL [2]
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [3]
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Meeting with Hovanes (Slow control)
- Translation tables [4]
- Light Monitoring System -- Arshak
- Simulations/Analysis