*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
+ | ** - HV long cable: Sammy and Mindy have to assemble 10 cables | ||
+ | ** - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] | ||
+ | ** - Fix front panel of two LV distribution boards, re-install the boards on the detector frame [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] | ||
+ | ** - LED: Started testing the prototype of the LMS (need to make the detector room light tight) | ||
+ | <!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
+ | ** Report from students [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_28_2024/student_report_06_28_2024.pptx] | ||
+ | ** Installation of HV cables [https://logbooks.jlab.org/entry/4313492][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_02_2024] | ||
+ | ::: - two remaining bundle of cables will be ready in about a week | ||
+ | ** Installation and testing cables and dividers [https://logbooks.jlab.org/entry/4314924] | ||
+ | ** Installation of long signal cables [https://logbooks.jlab.org/entry/4312667] | ||
+ | ** Installation LV patch panels and cables [https://logbooks.jlab.org/entry/4312759] | ||
+ | ** Installation of optical fibers [https://logbooks.jlab.org/entry/4311499] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ||
* '''Students''' -- Sasha | * '''Students''' -- Sasha | ||
+ | ** - Expect one student from Wuhan, waiting for the US visa | ||
* '''Beam tests with the PS''' | * '''Beam tests with the PS''' | ||
+ | *** measure shower beam profile and reconstruction in the crystal/LG transition region | ||
+ | *** (install prototype with 5x5 PbWO4 modules + ? LG) | ||
* '''Other hardware projects''' | * '''Other hardware projects''' | ||
+ | ** prototype of the ECAL veto counter (?) | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' | ||
** [https://halldweb.jlab.org/wiki/images/1/19/August-16-Status-Update.pdf Close shower separation studies] -- Laveen | ** [https://halldweb.jlab.org/wiki/images/1/19/August-16-Status-Update.pdf Close shower separation studies] -- Laveen | ||
*'''New manpower for the upcoming run and data analysis''', -- Liping | *'''New manpower for the upcoming run and data analysis''', -- Liping | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Bill, Laveen, Liping, Jane, Vlad, Sasha, Axel, Susan, Stjepan, S.T. | ||
+ | * Front panel of two LV distribution boards needed to be fixed | ||
+ | * 2 HV cable bundles each containing 9 cables are in Hall, 1 more bundle has been assembled | ||
+ | * Waiting for HV distribution boards, due in ~2 weeks | ||
+ | * 6 PMT divider layers remain to be installed | ||
+ | ** Found some common problems: weak solder joints, bad connectors | ||
+ | ** One short cable needed to be swapped out | ||
+ | ** Added velcro band to connect chains (supporting cables) together | ||
+ | * Laveen presented an update on 2-shower separation studies | ||
+ | ** Separation efficiency at small separation distances depends on energy asymmetry of two showers and total energy | ||
+ | * Liping reported that a professor from the China University of Geosciences (Wuhan) is interested in joining GlueX to work on JEF physics | ||
+ | * Vlad pointed out that we need to make sure that the test setup in one arm of the PS setup in the Hall D we have used in the past is restored | ||
+ | ** Could use this to measure shower profile + study lead glass-lead tungstate interface with small-scale prototype | ||
+ | *** Will need hardware design/CAD drawings for box to contain crystals and lead glass blocks | ||
+ | ** Test veto prototype? Thin scintillator paddles with wave-length shifting fibers | ||
+ | ** Sasha thinking about run plan for usage of this arm, will work on a wiki page |
Latest revision as of 16:28, 16 August 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- - two remaining bundle of cables will be ready in about a week
- Installation and testing cables and dividers [7]
- Installation of long signal cables [8]
- Installation LV patch panels and cables [9]
- Installation of optical fibers [10]
- Detector installation page
- Safety briefings
- Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation
- Close shower separation studies -- Laveen
- New manpower for the upcoming run and data analysis, -- Liping
Minutes
Attendees: Bill, Laveen, Liping, Jane, Vlad, Sasha, Axel, Susan, Stjepan, S.T.
- Front panel of two LV distribution boards needed to be fixed
- 2 HV cable bundles each containing 9 cables are in Hall, 1 more bundle has been assembled
- Waiting for HV distribution boards, due in ~2 weeks
- 6 PMT divider layers remain to be installed
- Found some common problems: weak solder joints, bad connectors
- One short cable needed to be swapped out
- Added velcro band to connect chains (supporting cables) together
- Laveen presented an update on 2-shower separation studies
- Separation efficiency at small separation distances depends on energy asymmetry of two showers and total energy
- Liping reported that a professor from the China University of Geosciences (Wuhan) is interested in joining GlueX to work on JEF physics
- Vlad pointed out that we need to make sure that the test setup in one arm of the PS setup in the Hall D we have used in the past is restored
- Could use this to measure shower profile + study lead glass-lead tungstate interface with small-scale prototype
- Will need hardware design/CAD drawings for box to contain crystals and lead glass blocks
- Test veto prototype? Thin scintillator paddles with wave-length shifting fibers
- Sasha thinking about run plan for usage of this arm, will work on a wiki page
- Could use this to measure shower profile + study lead glass-lead tungstate interface with small-scale prototype