* Notes:
 
* Notes:
 +
** Wayne is designing overall layout.
 
** Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
 
** Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
 
** May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
 
** May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
Line 10: Line 11:
 
** Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
 
** Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
 
** Platform is 172" x 160", cryo can will sit on top.
 
** Platform is 172" x 160", cryo can will sit on top.
 +
** Platform must be removed to swap coils, and all connections to it must be broken.
 
** Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
 
** Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
 
** Need come-alongs and anchors to move yokes and coils along rails.
 
** Need come-alongs and anchors to move yokes and coils along rails.
 +
  
 
* '''To Do:'''
 
* '''To Do:'''
Line 18: Line 21:
 
** Distribute Floyd's B field map for single coil, no cladding - George
 
** Distribute Floyd's B field map for single coil, no cladding - George
 
** Determine location of all components - Wayne
 
** Determine location of all components - Wayne
** Arrange for piping designer - George
 
*** Design piping to vent N2.
 
*** Design warm and cold He supply/return systems, LN2 supply system.
 
 
** Investigate sensitivity of electronic equipment to B fields - Elliott
 
** Investigate sensitivity of electronic equipment to B fields - Elliott
 
+
** Find spreader bar - George
 
+
** Verify we have all cryo transfer lines and U-tubes - Mark S
+
** Verify we can borrow heat exchanger from Hall A - George
+
** Order warm He and N2 piping - ?
+
** Retrieve rails from IU - ?
+
  
  
Line 33: Line 28:
  
 
* Notes:
 
* Notes:
 +
** Platform borrowed from Hall A.
 +
** Rails currently at IU.
 +
** Have or can borrow all material moving equipment, or will contract out to rigging firm.
 +
** Have or can borrow all tools needed.
 +
  
 
* '''To Do:'''
 
* '''To Do:'''
 +
** Design structures and mechanical components, route cables and cryo piping, etc. - Wayne
 +
** Arrange for piping designer - George
 +
*** Design piping to vent N2.
 +
*** Design warm and cold He supply/return systems, LN2 supply system.
 +
** Order warm He and N2 piping - ?
 +
** Retrieve rails from IU - ?
  
  
Line 42: Line 48:
  
 
* '''To Do:'''
 
* '''To Do:'''
 +
** Verify we have all cryo transfer lines and U-tubes - Mark S
 +
** Verify we can borrow heat exchanger from Hall A - George
  
  
Line 59: Line 67:
 
* Notes:
 
* Notes:
 
** Micro-review of PLC vendor choice completed, waiting for report.
 
** Micro-review of PLC vendor choice completed, waiting for report.
 +
** Need cryo, electrical, mechanical, and operations reviews.
 +
  
 
* '''To Do:'''
 
* '''To Do:'''
** Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review.
+
** Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
 +
** Write appropriate documentation - George, Mark S, Wayne and Elliott
 +
** Set up all reviews - George and Elliott

Revision as of 14:14, 18 June 2009

Notes and to-do lists for the solenoid coil tests this summer and fall.


Test Area

  • Notes:
    • Wayne is designing overall layout.
    • Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
    • May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
    • May need extra space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
    • Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
    • Platform is 172" x 160", cryo can will sit on top.
    • Platform must be removed to swap coils, and all connections to it must be broken.
    • Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
    • Need come-alongs and anchors to move yokes and coils along rails.


  • To Do:
    • Look into getting space in adjacent areas - George
    • Look into possibility of locating computer in control room - Elliott
    • Distribute Floyd's B field map for single coil, no cladding - George
    • Determine location of all components - Wayne
    • Investigate sensitivity of electronic equipment to B fields - Elliott
    • Find spreader bar - George


Infrastructure

  • Notes:
    • Platform borrowed from Hall A.
    • Rails currently at IU.
    • Have or can borrow all material moving equipment, or will contract out to rigging firm.
    • Have or can borrow all tools needed.


  • To Do:
    • Design structures and mechanical components, route cables and cryo piping, etc. - Wayne
    • Arrange for piping designer - George
      • Design piping to vent N2.
      • Design warm and cold He supply/return systems, LN2 supply system.
    • Order warm He and N2 piping - ?
    • Retrieve rails from IU - ?


Components

  • Notes:
  • To Do:
    • Verify we have all cryo transfer lines and U-tubes - Mark S
    • Verify we can borrow heat exchanger from Hall A - George


Staging

  • Notes:
    • Will instrument controls racks in F117, then move to Test Lab.
    • Will instrument for final 4-coil system.
  • To Do:
    • Rearrange F117 - Mark S and Beni
    • Get and move 3 racks into F117 - Mark S


Reviews

  • Notes:
    • Micro-review of PLC vendor choice completed, waiting for report.
    • Need cryo, electrical, mechanical, and operations reviews.


  • To Do:
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
    • Write appropriate documentation - George, Mark S, Wayne and Elliott