===Solenoid Coil Test Weekly Meeting===
 
===Solenoid Coil Test Weekly Meeting===
 +
 +
 +
'''This meeting was canceled!'''
 +
  
  
Line 25: Line 29:
 
** hardware and software requirements
 
** hardware and software requirements
 
* [[For_the_third_coil|To-do list]] for the next coil
 
* [[For_the_third_coil|To-do list]] for the next coil
 +
** measure UPS lifetime under operating conditions
 
* Coil 2 repair status
 
* Coil 2 repair status
 
* [http://irmis.sourceforge.net IRMIS]
 
* [http://irmis.sourceforge.net IRMIS]
 
* Preparing for moving into the hall
 
* Preparing for moving into the hall

Latest revision as of 17:26, 28 March 2011

Solenoid Coil Test Weekly Meeting

This meeting was canceled!


Location and Time

  • Fri 25-Mar-2011 9:30 am ARC 231

NOTE: we are back to ARC 231 again, hopefully for good!


Agenda

  • Coil 4 removal and Coil 3 repair and installation status
  • Improvements needed for coil 3
    • Danfysik power transistor
    • balancing quench detector given new inductance calculation and tap locations
    • document trip chains
    • trip sequence diagnosis system
    • slow dump still not working
    • new wiring
  • PLC system improvements
    • additional licenses and modules
  • New VME-based fast DAQ system
    • hardware and software requirements
  • To-do list for the next coil
    • measure UPS lifetime under operating conditions
  • Coil 2 repair status
  • IRMIS
  • Preparing for moving into the hall