= Minutes = | = Minutes = | ||
− | ''Attending: | + | ''Attending:Elton, Beni, Yi, Eugene, David (JLab); Zisis, Andrei (UofR); Javiera, Hayk, Iñaki, Alam, Kuleshov (USM). |
+ | |||
+ | # Announcements | ||
+ | # Review of Action Items | ||
+ | # Update from Athens: monitoring | ||
+ | #* Fernando has approved the drawings for the Fcal monitoring. | ||
+ | #* Elton: My understanding is that all parts are in for the Bcal boards. Stuffing and assembly will begin next Monday. | ||
+ | # Update from USM | ||
+ | ##[[Media:USMReport27.pdf|SiPM Update]] (Javiera) | ||
+ | ##* Third shipment of 520 SiPMs to JLab on Aug 31. Paperwork to smooth deliveries is underway. | ||
+ | ##* Zisis: Add expected completion date for each line in the table based on progress. | ||
+ | ##* Elton: Provide histograms of all measured units for each specification at T=20 deg C and V=1.2 V above breakdown. | ||
+ | ##* Elton: Send dump of data base. Hayk: Suggest to send the dump on a disk with the next shipment. | ||
+ | ##[[Media:Light-guide-report08-21.pdf|Light guides]] (Iñaki) | ||
+ | # Status of testing at JLab | ||
+ | # Beam Tests, Cosmics | ||
+ | # Simulations | ||
+ | # Other |
Revision as of 14:54, 21 August 2012
Teleconference Time: 11:00 a.m. EST
- ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
- Phone connection only upon request.
- +1-866-740-1260 : US and Canada
- +1-303-248-0285 : International
- then use participant code: 3421244# (the # is needed when using the phone)
- OR from www.readytalk.com type access code 3421244 into "join a meeting" without the # (you need java plugin)
Contents
Participant Direct Lines
- JLab Phone: in CC F326 is 757-269-6337 (usual room)
- JLab Phone in CC L207 is 757-269-7084
- Phone in the Regina Videoconference Suite is 306-585-4204
- Athens Phone: in Christina's office is 011-30-210-727-6947
Items for followup from previous meeting
-
Elton to check light guide delays versus FastTrack and inform us if we are on a critical path.- Current light guide schedule about 3 months behind schedule baseline. Estimated time to glue guides is 10 weeks. Estimated completion is late Jan. -> impact schedule float, but not significantly.
Presentations from recent meetings
Tentative Agenda
- Announcements
- Review of Action Items
- Update from Athens: monitoring
- Update from USM
- SiPM Update (Javiera)
- Light guides (Iñaki)
- Status of testing at JLab
- Beam Tests, Cosmics
- Simulations
- Other
Minutes
Attending:Elton, Beni, Yi, Eugene, David (JLab); Zisis, Andrei (UofR); Javiera, Hayk, Iñaki, Alam, Kuleshov (USM).
- Announcements
- Review of Action Items
- Update from Athens: monitoring
- Fernando has approved the drawings for the Fcal monitoring.
- Elton: My understanding is that all parts are in for the Bcal boards. Stuffing and assembly will begin next Monday.
- Update from USM
- SiPM Update (Javiera)
- Third shipment of 520 SiPMs to JLab on Aug 31. Paperwork to smooth deliveries is underway.
- Zisis: Add expected completion date for each line in the table based on progress.
- Elton: Provide histograms of all measured units for each specification at T=20 deg C and V=1.2 V above breakdown.
- Elton: Send dump of data base. Hayk: Suggest to send the dump on a disk with the next shipment.
- Light guides (Iñaki)
- SiPM Update (Javiera)
- Status of testing at JLab
- Beam Tests, Cosmics
- Simulations
- Other