Difference between revisions of "August 16, 2013 Installation"
From GlueXWiki
(Created page with "__TOC__ == Meeting Time and Place == Friday, August 16, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326 == Connections == To connect from the outside, pleas...") |
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/") |
||
(3 intermediate revisions by one other user not shown) | |||
Line 30: | Line 30: | ||
#* Impact of Magnet work on installation. | #* Impact of Magnet work on installation. | ||
# Updates to the Mechanical Installation Schedule ([[Media:June 2013 Install Schedule.pdf | Latest Rendition of Install Schedule]]) (Tim) | # Updates to the Mechanical Installation Schedule ([[Media:June 2013 Install Schedule.pdf | Latest Rendition of Install Schedule]]) (Tim) | ||
− | # Electronics Installation Schedule (Fernando) [[https:// | + | # Electronics Installation Schedule (Fernando) [[https://halldweb.jlab.org/wiki/index.php/Status_%26_Schedules | Schedule]] |
# [[Summer 2013 Manpower Contributions |Summer manpower]] | # [[Summer 2013 Manpower Contributions |Summer manpower]] | ||
# Trigger and DAQ needs during installation and commissioning. | # Trigger and DAQ needs during installation and commissioning. | ||
Line 41: | Line 41: | ||
#* BCAL Installation | #* BCAL Installation | ||
#* FCAL Installation | #* FCAL Installation | ||
− | #* FDC Installation | + | #* FDC Installation [http://www.jlab.org/Hall-D/detector/fdc/photographs/IMG_0706.JPG],[http://www.jlab.org/Hall-D/detector/fdc/photographs/IMG_0670.JPG],[http://www.jlab.org/Hall-D/detector/fdc/photographs/IMG_0716.JPG],[http://www.jlab.org/Hall-D/detector/fdc/photographs/IMG_0722.JPG] |
#* CDC Installation | #* CDC Installation | ||
#* TOF Installation | #* TOF Installation |
Latest revision as of 18:17, 31 March 2015
Contents
[hide]Meeting Time and Place
Friday, August 16, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone (supported on request only) dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Desktop Sharing
You can view the computer desktop in the meeting room at JLab via the web.
- Go to http://esnet.readytalk.com
- In the "join a meeting" box enter the Hall D code: 3421244
- Fill in the participant registration form.
Up to GlueX/Hall-D Installation Meetings
Action Items From Last Meeting
Agenda
- Announcements
- Magnet Status
- Impact of Magnet work on installation.
- Updates to the Mechanical Installation Schedule ( Latest Rendition of Install Schedule) (Tim)
- Electronics Installation Schedule (Fernando) [| Schedule]
- Summer manpower
- Trigger and DAQ needs during installation and commissioning.
- Installation Updates (Not a construction report)
- Counting House Infracstructure
- Trigger and DAQ Installation
- Slow Control Installation
- Tagger Magnet Installation
- BCAL Installation
- FCAL Installation
- FDC Installation [1],[2],[3],[4]
- CDC Installation
- TOF Installation
- Start Counter Installation
- Microscope Installation
- Tagger Array Installation
- Pair Spectrometer Installation
- A.O.B.