Difference between revisions of "Minutes-4-2-2015"

From GlueXWiki
Jump to: navigation, search
(Created page with "March 26, 2015 FDC+CDC meeting = Connection = # [https://halldweb.jlab.org/wiki/index.php/Connect_to_Bluejeans_Meetings Instructions for Bluejeans meeting connection] # FDC...")
 
(FDC update)
 
(13 intermediate revisions by the same user not shown)
Line 1: Line 1:
March 26, 2015 FDC+CDC meeting
+
April 2, 2015 FDC+CDC meeting
  
 
= Connection =
 
= Connection =
Line 9: Line 9:
 
= Agenda =
 
= Agenda =
  
 +
# Running at half energy
 
# Gas puzzle
 
# Gas puzzle
#* CO2 monitoring [http://www.jlab.org/Hall-D/detector/fdc/gas_system/DS_PMP_0013_2.pdf]
+
#* CO2 monitoring [http://www.jlab.org/Hall-D/detector/fdc/gas_system/co2_monitoring_04_02.pdf]
 
# CDC update (Beni, Mike)
 
# CDC update (Beni, Mike)
 
# FDC update (Lubomir)
 
# FDC update (Lubomir)
 +
#* [http://www.jlab.org/Hall-D/detector/fdc/spring2015run/HV_4c6_p2_04_02.png HV4_c6_2p amps][http://www.jlab.org/Hall-D/detector/fdc/spring2015run/HV_4c6_p2_04_02_volts.png HV4_c6_2p volts]
 +
#* 55Fe-source studies: [http://www.jlab.org/Hall-D/detector/fdc/55Festudies/55Fe_2200_spare_updown.pdf spare], [http://www.jlab.org/Hall-D/detector/fdc/55Festudies/55Fe_2200_FDC4_updown.pdf FDC4]
 
# Electronics (Fernando, Cody, Chris, Nick)
 
# Electronics (Fernando, Cody, Chris, Nick)
 
# Engineering
 
# Engineering
 
# Other
 
# Other
 
<!--
 
  
 
= Minutes =
 
= Minutes =
  
Participants: Naomi (CMU), Fernando, Dave, Chris, Nick, Cody, Beni, Simon, and Lubomir (JLab).
+
Participants: Curtis, Naomi(CMU), Sean(NU), Eugene, Luke, Mike, Dave, Chris, Nick, Cody, Beni, Simon, and Lubomir (JLab).
  
== Power outage issues ==
+
== Running at half energy ==
  
- After restoring the FDC LV, many channels showed "temperature failure". It turned out the fans of the LV crate (U2-2-BOT) were not blowing. After unplugging/plugging the power cord, the fans started operating. Fernando: most likely it is a control issue, also one has to find a way to read the fan speed remotely. The CDC LV crate had no problems.
+
- For the FDC we expect to have about the same e.m. background on the chambers, i.e. we will be limited by the same photon intensity as in the fall run. The number of pion tracks is expected to be about half of that in the fall. We asked for 16 hours beam time assuming we will have 8 hours at each of the two HV settings: 2200V and 2250V. As the HV filter boxes are expected to reduce the noise significantly, we ask for 16h run only at one setting - 2200V but at a lower discriminator threshold - thus compensating for the smaller number of tracks.
  
- After the outage, the chiller was turned on without touching the switch-off box, even the interlock should have prevented the box from turning on. Dave and Hovanes will look into this.
+
== Gas puzzle ==
  
- All the elements of the gas system were of UPS and it never stopped for the FDC. Beni turned off the CDC MFCs in the gas room because they were in a continuous mode (temporary), therefore the pressure in the CDC mixing tank went to zero. It would be interesting to measrue the Oxygen contamination in the CDC.
+
- The new pump has been installed in the EEL and data taken with the spare package using the certified gas mixture. On the attached plot: CO2 measurements (blue), atmospheric pressure (black), corrected measurements (red) using (dp/p)^2.4 pressure correction. This pump has variable flow, Nick and Chris made voltage control for that. Thus the flow was adjusted in this way, keeping the rotameter open completely, so that the pump doesn't create vacuum.  
  
== Gas puzzle ==
+
- The plan is to monitor the certified gas till Friday afternoon, then move the sensor to the Hall and monitor the CDC for one more day. On Saturday afternoon Beni will change the CO2 gas factor to 1.  
 
+
- The new pump for the CO2 sensor will come tomorrow. After calibration the sensor will be installed in the Hall to monitor the adjustment of the CDC gas mixture to 50/50.  
+
  
 
== CDC update ==
 
== CDC update ==
  
- Naomi showed interesting results (linked above) comparing two runs before/after Beni made several modifications of the gas mixing system. They demonstrate change of the drift time in the CDC by ~10%, but most noticeably big change in the gain. By analyzing more runs in between we should figure out what caused the changes.
+
- Naomi found in run 2451, some of the pedestals are wobbling by 100+/-3 units on a scale of hours. Could be temperature variations, in any case it is small compared to the thresholds of ~60.
  
 
== FDC update ==
 
== FDC update ==
  
- Lubomir studied the cathode resolution using the runs with 55Fe source, both with the FDC in the Hall and with the spare package. Cathodes can reconstruct the position of the wire (that was used as a trigger) with a surprisingly high precision. First plot shows the residual vs coordinate along the wire, where one see interesting structures with widths of ~100 microns. Even simple projection (second plot) gives a resolution of ~180 microns. These numbers should be divided by ~4 to get the cathode resolution along the wire, so we get 25-50 microns !?! Of course the advantage of the 55Fe source is that it gives a huge signal with a standard shape, which is not the case for the hits from the charged particle. Still this technique can be used to study systematic effects like cathode deformations.  
+
- The HV channel on FDC4 cell 6 sector 2p, developed a constant current of ~3 microamps (at the nominal 2200V) after being unstable for a week (current/voltage plots attached). Most likely the problem is outside of the gas volume and we may attempt to fix it sometimes when the FDC is pulled outside of the magnet.  
  
- One HV channel (FDC4 cell 6 sector 2p) shows unstable HV, going down from time to time by up to 7-8Volts, and jumping current up to 2-3 uA (two plots attached). By swapping cables, it was found the problem is in the detector. The current can be explained by the detector, but it is not clear why the HV is not stable.
+
- Interesting results with an 55Fe source shown on the plots: ratio of the upper strip to down strip charge as a function of the avalanche position along the wire used in the trigger for both tests, with the spare package and with FDC4 in the Hall. Apart from variations along the wire caused by some differences in the gains of the strips and position w.r.t. center of the strip, there are two images 10% apart. Beni proposed these are avalanches above and below the wire, but the avalanches develop so close to the wire that is difficult to explain the 10% difference.
  
 
== Electronics ==
 
== Electronics ==
  
- Beni answering Cody's question: the flash 125s should stay ON when the DAQ is not running, they don't consume a lot of power.
+
- The HV filter boxes will arrive next week and will be installed right away.  
  
 
== Engineering ==
 
== Engineering ==
  
- Yesterday morning we found a Fluorinert leak/drip at the connection of the return to the chiller. After fixing it one can still sniff leakage at almost all connections to the chiller, but since then the loss of Fluorinert was reduced significantly.
+
- We discussed if we can monitor spikes/glitches in the power, since we suspect some of the HV trips are related to that. Dave has such monitoring for the magnet, but needs to be put into the EPICS stream.
 
+
-->
+

Latest revision as of 15:05, 3 April 2015

April 2, 2015 FDC+CDC meeting

Connection

  1. Instructions for Bluejeans meeting connection
  2. FDC meeting ID: 290664653
  3. To join via a Web Browser, go to the page [1] https://bluejeans.com/290664653.

Agenda

  1. Running at half energy
  2. Gas puzzle
    • CO2 monitoring [2]
  3. CDC update (Beni, Mike)
  4. FDC update (Lubomir)
  5. Electronics (Fernando, Cody, Chris, Nick)
  6. Engineering
  7. Other

Minutes

Participants: Curtis, Naomi(CMU), Sean(NU), Eugene, Luke, Mike, Dave, Chris, Nick, Cody, Beni, Simon, and Lubomir (JLab).

Running at half energy

- For the FDC we expect to have about the same e.m. background on the chambers, i.e. we will be limited by the same photon intensity as in the fall run. The number of pion tracks is expected to be about half of that in the fall. We asked for 16 hours beam time assuming we will have 8 hours at each of the two HV settings: 2200V and 2250V. As the HV filter boxes are expected to reduce the noise significantly, we ask for 16h run only at one setting - 2200V but at a lower discriminator threshold - thus compensating for the smaller number of tracks.

Gas puzzle

- The new pump has been installed in the EEL and data taken with the spare package using the certified gas mixture. On the attached plot: CO2 measurements (blue), atmospheric pressure (black), corrected measurements (red) using (dp/p)^2.4 pressure correction. This pump has variable flow, Nick and Chris made voltage control for that. Thus the flow was adjusted in this way, keeping the rotameter open completely, so that the pump doesn't create vacuum.

- The plan is to monitor the certified gas till Friday afternoon, then move the sensor to the Hall and monitor the CDC for one more day. On Saturday afternoon Beni will change the CO2 gas factor to 1.

CDC update

- Naomi found in run 2451, some of the pedestals are wobbling by 100+/-3 units on a scale of hours. Could be temperature variations, in any case it is small compared to the thresholds of ~60.

FDC update

- The HV channel on FDC4 cell 6 sector 2p, developed a constant current of ~3 microamps (at the nominal 2200V) after being unstable for a week (current/voltage plots attached). Most likely the problem is outside of the gas volume and we may attempt to fix it sometimes when the FDC is pulled outside of the magnet.

- Interesting results with an 55Fe source shown on the plots: ratio of the upper strip to down strip charge as a function of the avalanche position along the wire used in the trigger for both tests, with the spare package and with FDC4 in the Hall. Apart from variations along the wire caused by some differences in the gains of the strips and position w.r.t. center of the strip, there are two images 10% apart. Beni proposed these are avalanches above and below the wire, but the avalanches develop so close to the wire that is difficult to explain the 10% difference.

Electronics

- The HV filter boxes will arrive next week and will be installed right away.

Engineering

- We discussed if we can monitor spikes/glitches in the power, since we suspect some of the HV trips are related to that. Dave has such monitoring for the magnet, but needs to be put into the EPICS stream.