Difference between revisions of "August 9, 2018 DIRC"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
(7 intermediate revisions by 3 users not shown) | |||
Line 21: | Line 21: | ||
#* Fabrication status update (Ernie and Jason) | #* Fabrication status update (Ernie and Jason) | ||
#** Component QA and assembly status at Bates | #** Component QA and assembly status at Bates | ||
− | #** | + | #** Verify lower box delivery [https://halldweb.jlab.org/wiki/index.php/File:Page3image256.jpg] |
− | #** | + | #** Quartz window flange modification |
+ | #** Delivery of back plate from Lesker (August 8?) | ||
+ | #** Mirror cutting and installation | ||
#* Dark box design (Jason) | #* Dark box design (Jason) | ||
#* PMT test fixture and cookies (Maria) | #* PMT test fixture and cookies (Maria) | ||
Line 29: | Line 31: | ||
#** Ernie to deliver on Sunday evening, August 12 | #** Ernie to deliver on Sunday evening, August 12 | ||
#** Packing list from Bates (Jason) | #** Packing list from Bates (Jason) | ||
− | #** Goals | + | #** Goals: |
#*** Test water tightness of optical box and interface with bar boxes | #*** Test water tightness of optical box and interface with bar boxes | ||
#*** Flow water through full system and establish controls, N2 purge, etc. | #*** Flow water through full system and establish controls, N2 purge, etc. | ||
+ | #*** [[Media:OB_install_procedure.pdf|OB Install Procedure]] | ||
# Mirror box laser alignment | # Mirror box laser alignment | ||
− | #* Update on geometry and laser projections (Bill) | + | #* Update on [https://halldweb.jlab.org/DocDB/0035/003581/002/2018_Aug_02.pdf geometry and laser projections], utilize Optical Box cradle (Bill/Stephanie) |
# Cabling and DAQ integration | # Cabling and DAQ integration | ||
− | #* Cabling | + | #* Cabling progressing (Tim, Fernando) |
− | #* | + | #* Sasha successfully read out SSP in DIRC crate with production DAQ, next install FPGA module for further testing |
+ | #* When data available from FPGA, EVIO parser can be written and translation table developed | ||
# Simulation studies (Maria and Roman) | # Simulation studies (Maria and Roman) | ||
#* Finalizing DIRC "as-build" geometry: support frames, etc. ([https://halldweb.jlab.org/wiki/images/c/cf/As_build_geometry_update.pdf Yunjie], Maria) | #* Finalizing DIRC "as-build" geometry: support frames, etc. ([https://halldweb.jlab.org/wiki/images/c/cf/As_build_geometry_update.pdf Yunjie], Maria) | ||
− | #* [https://www.dropbox.com/s/ | + | #* [https://www.dropbox.com/s/vr4doxegnedpg50/DIRC_writeup.pdf?dl=0 Documentation of LUT algorithm and time-based algorithm] by Maria |
− | #* Implementation of reconstruction in | + | #* Implementation of reconstruction in halld_recon library underway (Justin) |
# MAPMT testing (Bill and Andrew) | # MAPMT testing (Bill and Andrew) | ||
− | #* Magnetic field tests underway | + | #* Magnetic field tests underway this week |
− | #* Update | + | #* [https://halldweb.jlab.org/wiki/images/9/98/8_9_2018_MAPMT_test_update.pdf Magnetic Field Test Update] (Andrew) |
# [[Fall 2018 DIRC Commissioning|Commissioning plans]] | # [[Fall 2018 DIRC Commissioning|Commissioning plans]] | ||
# Reminder: [[Addressing ERR review recommendations]] | # Reminder: [[Addressing ERR review recommendations]] | ||
#* Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed by August 20 (close of Hall D for beam) | #* Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed by August 20 (close of Hall D for beam) | ||
# AOB | # AOB |
Latest revision as of 10:53, 9 August 2018
Meeting Information
GlueX DIRC Analysis Meeting
Thursday August 9, 2018
10:00 am, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- New meeting time for Fall semester: Doodle poll
- Optical box
- Fabrication status update (Ernie and Jason)
- Component QA and assembly status at Bates
- Verify lower box delivery [2]
- Quartz window flange modification
- Delivery of back plate from Lesker (August 8?)
- Mirror cutting and installation
- Dark box design (Jason)
- PMT test fixture and cookies (Maria)
- Fabrication status update (Ernie and Jason)
- Installation schedule discussion:
- Requirements for mechanical install of optical box: Aug 10 installation schedule
- Ernie to deliver on Sunday evening, August 12
- Packing list from Bates (Jason)
- Goals:
- Test water tightness of optical box and interface with bar boxes
- Flow water through full system and establish controls, N2 purge, etc.
- OB Install Procedure
- Requirements for mechanical install of optical box: Aug 10 installation schedule
- Mirror box laser alignment
- Update on geometry and laser projections, utilize Optical Box cradle (Bill/Stephanie)
- Cabling and DAQ integration
- Cabling progressing (Tim, Fernando)
- Sasha successfully read out SSP in DIRC crate with production DAQ, next install FPGA module for further testing
- When data available from FPGA, EVIO parser can be written and translation table developed
- Simulation studies (Maria and Roman)
- Finalizing DIRC "as-build" geometry: support frames, etc. (Yunjie, Maria)
- Documentation of LUT algorithm and time-based algorithm by Maria
- Implementation of reconstruction in halld_recon library underway (Justin)
- MAPMT testing (Bill and Andrew)
- Magnetic field tests underway this week
- Magnetic Field Test Update (Andrew)
- Commissioning plans
- Reminder: Addressing ERR review recommendations
- Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed by August 20 (close of Hall D for beam)
- AOB