Difference between revisions of "Fall-2018-Running"
From GlueXWiki
(→Modified Plan at Collaboration Meeting) |
(→Modified Plan at Collaboration Meeting) |
||
Line 8: | Line 8: | ||
* November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible) | * November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible) | ||
* November 26 to December 19 3 Weeks CompCal Commissioning | * November 26 to December 19 3 Weeks CompCal Commissioning | ||
+ | == Where do we stand? == | ||
+ | * There are 45 days in the 9/28 to 11/10 period. | ||
+ | * We have run 11 days and collected 13 billion triggers | ||
+ | * We have 34 days remaining, would expect an additional 40 billion triggers | ||
+ | * We now expect about 53 billion triggers | ||
+ | * Spring 2017: 47 billion | ||
+ | * Spring 2018: 145 billion | ||
+ | * Fall 2018: 53 billion (est) | ||
+ | == Discussion == | ||
+ | * The machine will run 11.6 GeV until 26 November, potentially 16 more days, or 19 billion more triggers. | ||
+ | * Fall 2018 could be ~72 billion triggers (1/2 of Spring 2018). | ||
+ | * Such a change means CompCal Commissioning is cut to 1 week? |
Revision as of 09:25, 9 October 2018
_ _Original Plan
- August 22 to October 28 9.5 Weeks of Running Complete GlueX Phase I
- October 29 to November 19 3 Weeks Installation of CompCal and DIRC
- November 19 to December 19 4 Weeks CompCal and DIRC Commissioning
Modified Plan at Collaboration Meeting
- September 28 to November 10 6 Weeks GlueX Phase I
- November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible)
- November 26 to December 19 3 Weeks CompCal Commissioning
Where do we stand?
- There are 45 days in the 9/28 to 11/10 period.
- We have run 11 days and collected 13 billion triggers
- We have 34 days remaining, would expect an additional 40 billion triggers
- We now expect about 53 billion triggers
- Spring 2017: 47 billion
- Spring 2018: 145 billion
- Fall 2018: 53 billion (est)
Discussion
- The machine will run 11.6 GeV until 26 November, potentially 16 more days, or 19 billion more triggers.
- Fall 2018 could be ~72 billion triggers (1/2 of Spring 2018).
- Such a change means CompCal Commissioning is cut to 1 week?