Difference between revisions of "April 2, 2020 CPP Design Meeting"
From GlueXWiki
(→Meeting Time and Place =) |
(→Minutes and Action Items) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 16: | Line 16: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
− | * | + | *Reviewed minutes of last meeting |
+ | * We looked at Rory's pictures and discussed the 3D model that Stephanie shared | ||
+ | * looking at space on platform, we decided to leave the vertical cable managers so we have some space margin in the future | ||
+ | * Need to develop a dimensional layout of 3D model -- Stephanie | ||
+ | ** Note: The chamber currently in the hall has different thickness dimensions than the new ones | ||
+ | ** New chambers are 2.09" thick skin to skin | ||
+ | * Need to develop an installation procedure -- Tim/Stephanie | ||
+ | * Need to separate the 2 DS chambers for the electronics RF shielding | ||
+ | ** Rory to supply the gauge and dimensions of the shield | ||
+ | ** Stephanie to update geometry in 3D model | ||
+ | * Floor rail system design needed to allow CPP to move along with the FCAl platform | ||
+ | ** Tim to supply sketch | ||
+ | ** Stephanie to create 3D model and drawings | ||
+ | * Dark Room Structure | ||
+ | ** Tim to supply sketch for structural needs | ||
+ | ** Stephanie to update 3D model and create drawings | ||
+ | ** New structural members need to be installed before skin removal | ||
+ | * Next meeting to be 1:30 to avert a time conflict |
Latest revision as of 08:20, 6 April 2020
Meeting Time and Place =
Thursday April 2, 2020, 1pm Bluejeans https://bluejeans.com/239719940
- Present - Elton, Dave, Stephanie, Llya, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/February_27,_2020_CPP_Design_Meeting#Minutes_and_Action_Items
- Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf
- 3D model
- Things to work out
- Electronics shielding Media:Muon_Chamber_Shielding.pdf
- Grounding Media:Muon_Chamber_dimensions.pdf
- Complete structural analysis
- Develop installation plan
Minutes and Action Items
- Reviewed minutes of last meeting
- We looked at Rory's pictures and discussed the 3D model that Stephanie shared
- looking at space on platform, we decided to leave the vertical cable managers so we have some space margin in the future
- Need to develop a dimensional layout of 3D model -- Stephanie
- Note: The chamber currently in the hall has different thickness dimensions than the new ones
- New chambers are 2.09" thick skin to skin
- Need to develop an installation procedure -- Tim/Stephanie
- Need to separate the 2 DS chambers for the electronics RF shielding
- Rory to supply the gauge and dimensions of the shield
- Stephanie to update geometry in 3D model
- Floor rail system design needed to allow CPP to move along with the FCAl platform
- Tim to supply sketch
- Stephanie to create 3D model and drawings
- Dark Room Structure
- Tim to supply sketch for structural needs
- Stephanie to update 3D model and create drawings
- New structural members need to be installed before skin removal
- Next meeting to be 1:30 to avert a time conflict