+ | =Minutes= | ||
+ | Attendees: Phil, Igal, Zisis, Liping, Sasha, Vlad, Jane, Jon, Olga, S.T. | ||
+ | * All remaining optical fibers have been cut and donuts attached | ||
+ | ** Still need polishing; Sasha to get driver from Arshak to use polishing machine | ||
+ | ** Design for LMS installation to be finalized within about a week | ||
+ | * Received all PCBs for PMT dividers | ||
+ | ** Will proceed with attaching sockets | ||
+ | ** Each PMT divider will need to be checked | ||
+ | * Installation of FCAL2 modules almost done, only 3 rows remain | ||
+ | ** Found and put aside 2 modules with lost PMT vacuum | ||
+ | * Sasha working on keeping detector support group involved, also hope to get help from fast electronics group | ||
+ | *Liping's proposal for symposium at April APS meeting was approved |
Latest revision as of 13:14, 6 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Module fabrication -- Sasha
- All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [3] - done
- All crystals moved to Hall D[4] [5][6] - done
- Tested, labeled, and bundled all 100 (+ 2 spares) [7] signal cables connected from the flash ADC to the patch panel [8] - done
- Test and label 1100 short signal cables - ongoing
- Tested fabricated modules using LMS [9] - done (need to update the wiki page)
- Cutting optical fibers and gluing plastic caps [10], waiting for 7600 ft of optical fibers
- Report from students
- Refurbished (remove soldering bumps and rewrap) 42 modules. One more layer of the detector will be installed today.
- Need to wrap and fabricate about 30 modules using newly received crystals (will replace some already existing modules with low-quality crystals). Plan to finish with this during next week [11].
- Tested and labeled 120 HV cables
- Preparing optical fibers for the LMS
- Testing of PMT dividers -- Sasha / Vlad
- - Received all divider PCBs. Preparing test setup. Will proceed with testing during next week
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation [14][15][16]
- Detector installation page
- Updates from the meetings with Tim's group [17]
- Discussion of the FCAL2 installation procedures [18]
- Final mapping of low-voltage cables
- Mindy continues with wrapping crystals and soldering wires to sockets.
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Analysis/Simulation
Minutes
Attendees: Phil, Igal, Zisis, Liping, Sasha, Vlad, Jane, Jon, Olga, S.T.
- All remaining optical fibers have been cut and donuts attached
- Still need polishing; Sasha to get driver from Arshak to use polishing machine
- Design for LMS installation to be finalized within about a week
- Received all PCBs for PMT dividers
- Will proceed with attaching sockets
- Each PMT divider will need to be checked
- Installation of FCAL2 modules almost done, only 3 rows remain
- Found and put aside 2 modules with lost PMT vacuum
- Sasha working on keeping detector support group involved, also hope to get help from fast electronics group
- Liping's proposal for symposium at April APS meeting was approved