Difference between revisions of "September 10, 2024 KLONG CPS Design Meeting"
From GlueXWiki
(→Agenda) |
(→Minutes) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 17: | Line 17: | ||
** Collimator layout | ** Collimator layout | ||
** Magnetic shielding | ** Magnetic shielding | ||
+ | ** FSD detector | ||
+ | * Absorber shielding layout | ||
* Lead brick painting is 60% done and all due back in October | * Lead brick painting is 60% done and all due back in October | ||
** Additional 1200 painted lead bricks in PR system | ** Additional 1200 painted lead bricks in PR system | ||
Line 23: | Line 25: | ||
== Minutes == | == Minutes == | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Latest revision as of 11:40, 10 September 2024
Meeting Time and Place
Tuesday, September 10, 2024, 1:00pm Hall D Counting House
- Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard
Agenda
- Review minutes from last meeting https://halldweb.jlab.org/wiki/index.php/August_13,_2024_KLONG_CPS_Design_Meeting
- FSD Detector
- Power supply status -
- Magnet update (Josh/Stephanie)
- Copper cooling update -
- Beamline upstream of magnet
- 370um beryllium window with 4.5" flange available -
- Collimator layout
- Magnetic shielding
- FSD detector
- Absorber shielding layout
- Lead brick painting is 60% done and all due back in October
- Additional 1200 painted lead bricks in PR system
- DeGauss test -
- Working on ANSYS transient thermal and FLUENT/CFX models