Difference between revisions of "OWG Meeting 11-Nov-2009"
From GlueXWiki
m |
m (Text replacement - "http://argus.phys.uregina.ca/cgi-bin/private" to "https://halldweb.jlab.org/doc-private") |
||
(8 intermediate revisions by one other user not shown) | |||
Line 5: | Line 5: | ||
* Review of minutes from [[OWG Meeting 28-Oct-2009 | 28-Oct-2009]] meeting | * Review of minutes from [[OWG Meeting 28-Oct-2009 | 28-Oct-2009]] meeting | ||
* Update from DAQ Group - Dave A | * Update from DAQ Group - Dave A | ||
− | * Linux ROC development - Bryan | + | * [[Media:11nov2009_moffit.pdf|Linux ROC development]] - Bryan |
− | * Brief report from ICALEPCS 2009 - Elliott | + | * Brief report from [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=1385 EPICS collaboration meeting and ICALEPCS 2009 conference] - Elliott |
* Coil test update - Elliott | * Coil test update - Elliott | ||
* Other electronics and trigger status reports - Chris, Ben, Ed, Alex, Dave | * Other electronics and trigger status reports - Chris, Ben, Ed, Alex, Dave | ||
Line 26: | Line 26: | ||
− | 1:30 PM Wed | + | 1:30 PM Wed 9-Dec-2009 |
Line 35: | Line 35: | ||
=Minutes= | =Minutes= | ||
+ | 11nov2009_moffit.pdf | ||
+ | Attendees: Elliott W, Simon T, Mark I, Alex S, Bryan M, Carl t, Dave A, Ed J, Eugent C. | ||
− | + | ||
+ | '''DAQ Update''' | ||
+ | |||
+ | Dave A discussed the current status of and recent project in the JLab DAQ group: | ||
+ | |||
+ | * DAQ goup now fully staffed, recent hires Bryan Moffit and William Gu. | ||
+ | * Have enough staff to meet 12 GeV obligations and deliver CODA 3 on time. | ||
+ | * Bryan recently working on Linux ROC, William working on TI and TD boards. | ||
+ | * CODA 2.6.1 release soon, COOL-based run control state machine. | ||
+ | ** uses latest cMsg and AFECS | ||
+ | * Haven't started working on farm software yet. | ||
+ | * Carl is working on fixing remaining cMsg VxWorks bugs. | ||
+ | |||
+ | |||
+ | '''Linux ROC''' | ||
+ | |||
+ | * See Bryan's slides (link above) for more details; | ||
+ | * Using the GE FANUC dual-core VME board. | ||
+ | * Has 4 GB flash memory, Tempe chip (interface to VME). | ||
+ | * Supports 2ESST. | ||
+ | * Has longer interrupt latency and DMA setup than the Motorola PowerPC board, but this is not an issue. | ||
+ | * Bryan had to modify the GE-supplied software to get better performance, including the Tempe libs. | ||
+ | * The F1, FADC, and TI libs now work with the GE FANUC board. | ||
+ | * Worked on scheduling, latencies, DMA speeds. | ||
+ | * Improving core mgmt for threads gained 20 micro-sec. | ||
+ | * Not using any version of real-time Linux, only real-time extensions. | ||
+ | |||
+ | |||
+ | |||
+ | '''ICALEPCS 2009''' | ||
+ | |||
+ | Elliott reported on the EPICS collaboration meeting and ICALEPCS 2009 conference held in Kobe, Japan. See his slides (link above) for details. | ||
+ | |||
+ | |||
+ | |||
+ | '''Coil Test''' | ||
+ | |||
+ | Elliott gave a brief update on the status of the coil test. | ||
+ | |||
+ | * Steady progress in controls, but problems being found in the coils themselves. | ||
+ | * Solenoid review coming up next week. | ||
+ | * Should be able to use QWeak area nearby. | ||
+ | * New tech hires helping a lot! | ||
+ | * Most instrumentation ordered, a few items left. | ||
+ | * Incorrect wire used for cryo sensors, must be replaced in all four coils. | ||
+ | * Planning to work on three coils for other reasons so replacing wire not a problem. | ||
+ | * Will have to open coil 4 just to replace wire. | ||
+ | * Coil test schedule now extending into late 2010 or beyond. |
Latest revision as of 17:13, 24 February 2017
Contents
Agenda
- Announcements -
- Review of minutes from 28-Oct-2009 meeting
- Update from DAQ Group - Dave A
- Linux ROC development - Bryan
- Brief report from EPICS collaboration meeting and ICALEPCS 2009 conference - Elliott
- Coil test update - Elliott
- Other electronics and trigger status reports - Chris, Ben, Ed, Alex, Dave
Time/Location
1:30 PM Wed 11-Nov-2009 CC F326
Announcements
Next Meeting
1:30 PM Wed 9-Dec-2009
New Action Items from this Meeting
Minutes
11nov2009_moffit.pdf Attendees: Elliott W, Simon T, Mark I, Alex S, Bryan M, Carl t, Dave A, Ed J, Eugent C.
DAQ Update
Dave A discussed the current status of and recent project in the JLab DAQ group:
- DAQ goup now fully staffed, recent hires Bryan Moffit and William Gu.
- Have enough staff to meet 12 GeV obligations and deliver CODA 3 on time.
- Bryan recently working on Linux ROC, William working on TI and TD boards.
- CODA 2.6.1 release soon, COOL-based run control state machine.
- uses latest cMsg and AFECS
- Haven't started working on farm software yet.
- Carl is working on fixing remaining cMsg VxWorks bugs.
Linux ROC
- See Bryan's slides (link above) for more details;
- Using the GE FANUC dual-core VME board.
- Has 4 GB flash memory, Tempe chip (interface to VME).
- Supports 2ESST.
- Has longer interrupt latency and DMA setup than the Motorola PowerPC board, but this is not an issue.
- Bryan had to modify the GE-supplied software to get better performance, including the Tempe libs.
- The F1, FADC, and TI libs now work with the GE FANUC board.
- Worked on scheduling, latencies, DMA speeds.
- Improving core mgmt for threads gained 20 micro-sec.
- Not using any version of real-time Linux, only real-time extensions.
ICALEPCS 2009
Elliott reported on the EPICS collaboration meeting and ICALEPCS 2009 conference held in Kobe, Japan. See his slides (link above) for details.
Coil Test
Elliott gave a brief update on the status of the coil test.
- Steady progress in controls, but problems being found in the coils themselves.
- Solenoid review coming up next week.
- Should be able to use QWeak area nearby.
- New tech hires helping a lot!
- Most instrumentation ordered, a few items left.
- Incorrect wire used for cryo sensors, must be replaced in all four coils.
- Planning to work on three coils for other reasons so replacing wire not a problem.
- Will have to open coil 4 just to replace wire.