Difference between revisions of "For the third coil"
From GlueXWiki
m |
m |
||
(20 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
* Wiring | * Wiring | ||
− | ** rewire for coil 3 subcoils | + | ** rewire for coil 3 subcoils - '''done 25-Apr-2011''' |
− | ** | + | ** 20 kOhm protection resistors for coil taps if needed for quench detector balancing - '''not needed 7-Apr-2011''' |
− | ** | + | ** document trip chains |
− | + | ** label circuit breakers | |
− | ** | + | |
* Danfysik power supply | * Danfysik power supply | ||
− | ** fix broken transistor | + | ** add new readout channels - '''done 25-apr-2011''' |
+ | ** fix broken transistor - '''done 20-Apr-2011''' | ||
** commission fault sequencer | ** commission fault sequencer | ||
** fix slow dump | ** fix slow dump | ||
** understand ramp-down mechanism | ** understand ramp-down mechanism | ||
− | ** understand varying fast dump time constant | + | ** understand varying fast dump time constant - '''possibly understood 8-Apr-2011, needs verification''' |
** choose ground fault detection mechanism | ** choose ground fault detection mechanism | ||
+ | ** cover holes in cabinet - '''done 8-Apr-2011''' | ||
* Danfysik quench detector | * Danfysik quench detector | ||
− | ** implement divider circuit upstream of QD to eliminate | + | ** install bias pot on remaining three channels - '''done 7-Apr-2011''' |
+ | ** implement divider circuit upstream of QD to eliminate effect of coil imbalances - '''not needed 7-Apr-2011''' | ||
+ | ** install trip test points | ||
* Instrumentation | * Instrumentation | ||
− | ** ensure all devices on clean power | + | ** ensure all devices on clean power with good grounds - '''done 8-apr-2011''' |
− | ** check out Newport controllers, flow switch, replace if needed | + | ** check out Newport controllers, flow switch, replace if needed - '''done 25-apr-2011''' |
− | ** implement system to isolate fault detectors and determine time sequence of trips | + | ** implement system to isolate fault detectors and determine time sequence of trips - '''postponed 8-Apr-2011''' |
− | ** understand spikes on shunt Newport | + | ** understand spikes on shunt Newport - '''may never understand them...''' |
− | ** understand effect of B field on all sensors, move devices if needed | + | ** understand effect of B field on all sensors, move devices if needed - '''devices moved 8-Apr-2011''' |
** monitor circuit breakers? | ** monitor circuit breakers? | ||
− | * NI USB device | + | * NI USB device - '''replaced by VME DAQ system 7-Apr-2011''' |
** rework Zener/divider box, needs to be fully bipolar | ** rework Zener/divider box, needs to be fully bipolar | ||
** eliminate noise | ** eliminate noise | ||
+ | |||
+ | |||
+ | * VME-based fast DAQ | ||
+ | ** get hardware, test in lab - '''done 7-Apr-2011''' | ||
+ | ** write software, test in lab - '''done 25-Apr-2011''' | ||
+ | ** connect to apparatus - '''done 25-Apr-2011''' | ||
+ | ** real-time graphics | ||
* A-B HMI improvements | * A-B HMI improvements | ||
− | ** upgrade to 100 screen license | + | ** upgrade to 100 screen license - '''done 6-May-2011''' |
− | ** implement fault sequence screens | + | ** implement fault sequence screens if system implemented - '''not implemented 8-Apr-2011''' |
* A-B PLC program improvements | * A-B PLC program improvements | ||
− | ** | + | ** mods for new coil configuration - '''done 25-Apr-2011''' |
* EPICS | * EPICS | ||
+ | ** new channels | ||
Line 52: | Line 63: | ||
** update for latest tags and drawings | ** update for latest tags and drawings | ||
+ | |||
+ | * Auxiliary tests | ||
+ | ** requirements, setup for aux tests - '''done 12-May-2011''' | ||
+ | |||
+ | |||
+ | * Reenable cron job | ||
+ | ** when cooldown commences, end when warmed up - '''done 1-May-2011''' | ||
'''For the hall''' | '''For the hall''' | ||
* note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec | * note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec | ||
+ | * need travelers for coil installation. | ||
* should we install a UPS on the Danfysik contactor and control boards? | * should we install a UPS on the Danfysik contactor and control boards? | ||
+ | * should we install a second contactor in the Danfysik power supply? | ||
* do we need additional valves, check valves, bypasses, whatever? | * do we need additional valves, check valves, bypasses, whatever? | ||
* do we need Dataforth voltage attenuators on coil tap channels? | * do we need Dataforth voltage attenuators on coil tap channels? | ||
Line 63: | Line 83: | ||
* should we monitor all relays? | * should we monitor all relays? | ||
* what is the effect of B field on sensors/relays? should some instrumentation be relocated? | * what is the effect of B field on sensors/relays? should some instrumentation be relocated? | ||
+ | * do we need new flow sensors, or should they be relocated? | ||
+ | * lock box for power supply key | ||
+ | * more ethernet power strips | ||
+ | * use custom ("add-on") instructions to simplify PLC code |
Latest revision as of 16:18, 13 May 2011
To-do list
- Wiring
- rewire for coil 3 subcoils - done 25-Apr-2011
- 20 kOhm protection resistors for coil taps if needed for quench detector balancing - not needed 7-Apr-2011
- document trip chains
- label circuit breakers
- Danfysik power supply
- add new readout channels - done 25-apr-2011
- fix broken transistor - done 20-Apr-2011
- commission fault sequencer
- fix slow dump
- understand ramp-down mechanism
- understand varying fast dump time constant - possibly understood 8-Apr-2011, needs verification
- choose ground fault detection mechanism
- cover holes in cabinet - done 8-Apr-2011
- Danfysik quench detector
- install bias pot on remaining three channels - done 7-Apr-2011
- implement divider circuit upstream of QD to eliminate effect of coil imbalances - not needed 7-Apr-2011
- install trip test points
- Instrumentation
- ensure all devices on clean power with good grounds - done 8-apr-2011
- check out Newport controllers, flow switch, replace if needed - done 25-apr-2011
- implement system to isolate fault detectors and determine time sequence of trips - postponed 8-Apr-2011
- understand spikes on shunt Newport - may never understand them...
- understand effect of B field on all sensors, move devices if needed - devices moved 8-Apr-2011
- monitor circuit breakers?
- NI USB device - replaced by VME DAQ system 7-Apr-2011
- rework Zener/divider box, needs to be fully bipolar
- eliminate noise
- VME-based fast DAQ
- get hardware, test in lab - done 7-Apr-2011
- write software, test in lab - done 25-Apr-2011
- connect to apparatus - done 25-Apr-2011
- real-time graphics
- A-B HMI improvements
- upgrade to 100 screen license - done 6-May-2011
- implement fault sequence screens if system implemented - not implemented 8-Apr-2011
- A-B PLC program improvements
- mods for new coil configuration - done 25-Apr-2011
- EPICS
- new channels
- EWEB screens
- update for latest tags and drawings
- Auxiliary tests
- requirements, setup for aux tests - done 12-May-2011
- Reenable cron job
- when cooldown commences, end when warmed up - done 1-May-2011
For the hall
- note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
- need travelers for coil installation.
- should we install a UPS on the Danfysik contactor and control boards?
- should we install a second contactor in the Danfysik power supply?
- do we need additional valves, check valves, bypasses, whatever?
- do we need Dataforth voltage attenuators on coil tap channels?
- do we need active isolation of coil tap channels, etc?
- should we monitor all circuit breakers?
- should we monitor all relays?
- what is the effect of B field on sensors/relays? should some instrumentation be relocated?
- do we need new flow sensors, or should they be relocated?
- lock box for power supply key
- more ethernet power strips
- use custom ("add-on") instructions to simplify PLC code