Line 23: | Line 23: | ||
# Announcements | # Announcements | ||
# Updates to the Mechanical Installation Schedule ([[Media:Mar 2013 Install Schedule.pdf | Latest Rendition of Install Schedule]]) (Tim) | # Updates to the Mechanical Installation Schedule ([[Media:Mar 2013 Install Schedule.pdf | Latest Rendition of Install Schedule]]) (Tim) | ||
− | # Electronics Installation Schedule (Fernando) [[https:// | + | # Electronics Installation Schedule (Fernando) [[https://halldweb.jlab.org/wiki/index.php/Status_%26_Schedules | Schedule]] |
# [[Summer 2013 Manpower Contributions |Summer manpower]] | # [[Summer 2013 Manpower Contributions |Summer manpower]] | ||
# Magnet Mapping (Tim)([[Media:Tagger mapping.jpg | Tagger Magnet Mapping system]]) | # Magnet Mapping (Tim)([[Media:Tagger mapping.jpg | Tagger Magnet Mapping system]]) | ||
# Tagger Magnet Installation ([[Media:Vacuum chamber test fit.jpg | Vacuum chamber test fit]]) | # Tagger Magnet Installation ([[Media:Vacuum chamber test fit.jpg | Vacuum chamber test fit]]) | ||
− | # [ | + | # Microscope Installation |
+ | #* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=2200 Tagger microscope installation & commissioning document] | ||
+ | #* Signal cable lengths | ||
# Tagger Array Installation | # Tagger Array Installation | ||
# Pair Spectrometer Installation | # Pair Spectrometer Installation |
Latest revision as of 17:12, 24 February 2017
Meeting Time and Place
Friday, May 10, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone (supported on request only) dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Up to GlueX/Hall-D Installation Meetings
Action Items From Last Meeting
Agenda
- Announcements
- Updates to the Mechanical Installation Schedule ( Latest Rendition of Install Schedule) (Tim)
- Electronics Installation Schedule (Fernando) [| Schedule]
- Summer manpower
- Magnet Mapping (Tim)( Tagger Magnet Mapping system)
- Tagger Magnet Installation ( Vacuum chamber test fit)
- Microscope Installation
- Tagger microscope installation & commissioning document
- Signal cable lengths
- Tagger Array Installation
- Pair Spectrometer Installation
- BCAL Installation ( BCAL assy in hall)
- FCAL Insatllation
- TOF Installation
- FDC Installation document, and short presentation
- CDC Installation
- A.O.B.