== Meeting General Agenda == | == Meeting General Agenda == | ||
+ | |||
+ | [[Run Planning Meeting Notes, Mar 9 - Mar 15, 2017]] | ||
+ | |||
+ | [[Run Planning Meeting Notes, Mar 2 - Mar 8, 2017]] | ||
+ | |||
+ | [[Run Planning Meeting Notes, Feb 23- Mar 1, 2017]] | ||
+ | |||
+ | [[Run Planning Meeting Notes, Feb 16-Feb 22, 2017]] | ||
+ | |||
+ | [[Run Planning Meeting Notes, Feb 9-Feb 15, 2017]] | ||
== Connect Information == | == Connect Information == | ||
Line 25: | Line 35: | ||
==Beam and Hall configuration == | ==Beam and Hall configuration == | ||
− | * Beam energy expected: 11. | + | * Beam energy expected: 11.640 GeV (value from Fall 2017 measurement). |
* Solenoid on at 1350A. Any field changes should be avoided if possible. | * Solenoid on at 1350A. Any field changes should be avoided if possible. | ||
− | * Beam current: | + | * CW Beam current: |
− | * FFB on or Position Slow Lock on (FFB doesn't operate below 50nA). | + | ** Range: 1 nA-1.5 μA. 250 MHz frequency. |
+ | ** Standard production running expected at ~200 nA on 4·10<sup>-4</sup> R.L. radiator. | ||
+ | ** RSAD limit for most of the run, excluding high intensity tests: 250 nA on 4·10<sup>-4</sup> R.L. radiator. | ||
+ | * FFB on or Position Slow Lock on (FFB doesn't operate below 50nA). | ||
* Radiators: | * Radiators: | ||
**Goniometer diamond radiators: | **Goniometer diamond radiators: | ||
Line 37: | Line 50: | ||
**We also have one 10 μm Al radiator. | **We also have one 10 μm Al radiator. | ||
**Amorphous | **Amorphous | ||
− | *** 1. | + | *** 1.64 µm Al (1.86·10<sup>-5</sup> R.L., see [https://logbooks.jlab.org/entry/3631428 study]) |
*** 10 µm Al (11.2·10<sup>-5</sup> R.L.) | *** 10 µm Al (11.2·10<sup>-5</sup> R.L.) | ||
*** 30 µm Al (33.7·10<sup>-5</sup> R.L.) | *** 30 µm Al (33.7·10<sup>-5</sup> R.L.) | ||
Line 54: | Line 67: | ||
# Jan. 30th-Mar. 22nd: Hall D Spring run. | # Jan. 30th-Mar. 22nd: Hall D Spring run. | ||
# Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery. | # Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery. | ||
+ | |||
+ | * overall plan and priorities: | ||
+ | #The first priority is to do the Halls B and C KPP (key performance parameters). | ||
+ | #The second priority is to finish commissioning the 5-pass separator and to ensure we can reliably run with it. This is in preparation for the Fall 17 run when all halls will be a 5-pass (Hall D at 5.5 pass). | ||
+ | #*The above implies that Hall D should be run continuously at 5.5 pass and hence, the Hall D physics run is tie to priority #2. | ||
+ | #*Hall B starts its KPP run (3-pass) on Feb. 3rd. With smooth running, it should achieve the KPP goals in a day or two. Then, it shuts down. | ||
+ | #*Hall C starts its KPP run (3-pass) around March 7th. It will then continue running at 1-pass for spectrometer commissioning (if its magnets are cold and ready). Then, if time permit before the end of the spring run, they may start their physics program at 5-pass. | ||
+ | #*Hall A will be used for its beam-dump when Hall C is down, so that a high current beam can be run in the machine when Hall B and D are running. This high current beam will stabilize the beam orbit in the machine. Hall A may take advantage of receiving beam by opportunistically running its argon experiment. In that case, it will be at 1-pass. | ||
* Experiment: GlueX [https://misportal.jlab.org/mis/physics/experiments/searchProposals.cfm?paramHall=D¶mExperimentEnergy=12GeV¶mExperimentStatusList=A,G E12-06-102] Production | * Experiment: GlueX [https://misportal.jlab.org/mis/physics/experiments/searchProposals.cfm?paramHall=D¶mExperimentEnergy=12GeV¶mExperimentStatusList=A,G E12-06-102] Production | ||
Line 100: | Line 121: | ||
== Runplan == | == Runplan == | ||
− | + | #Verify electron beam quality and establish photon beam (assume 1 day). | |
− | # | + | #*<b>Ion Chambers trip threshold must be set using Al. radiators</b> |
− | #*<b>Ion Chambers trip threshold must be set.</b> | + | |
#*Tune electron beam with radiator retracted | #*Tune electron beam with radiator retracted | ||
− | #**<b> | + | #**<b>Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position. </b> |
− | + | ||
#***Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA) | #***Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA) | ||
− | #****RAD102_P1 <span style="color:#ff00ff">~ | + | #****RAD102_P1 <span style="color:#ff00ff">~ 10 mrad/hr</span> (tagger area, gammas, between tagger and dump) |
− | #****RAD102_P2 <span style="color:#ff00ff">~ | + | #****RAD102_P2 <span style="color:#ff00ff">~ 30 mrad/hr</span> (tagger area, gammas, on goniometer). |
#****RAD102_P3 <span style="color:#ff00ff">~ 0.1 mrem/hr</span> (tagger area, neutrons, near electronics racks) | #****RAD102_P3 <span style="color:#ff00ff">~ 0.1 mrem/hr</span> (tagger area, neutrons, near electronics racks) | ||
#****RAD508_P1 <span style="color:#ff00ff">< 0.1 mrad/hr</span> (collimator cave, gammas). | #****RAD508_P1 <span style="color:#ff00ff">< 0.1 mrad/hr</span> (collimator cave, gammas). | ||
− | #****RAD508_P2 <span style="color:#ff00ff"> | + | #****RAD508_P2 <span style="color:#ff00ff">~ 0. mrad/hr</span> (Hall. Neutrons). |
#**<b>Hall D tagger CARMS, Ion Chamber and BLM threshold for beam trips should not be changed without approval of Hall D leader.</b> | #**<b>Hall D tagger CARMS, Ion Chamber and BLM threshold for beam trips should not be changed without approval of Hall D leader.</b> | ||
− | #*Check bleedthrough level. 10min Hovanes. <font color="red">Hall A needs to be running</font> | + | <!--#*Check bleedthrough level. 10min Hovanes. <font color="red">Hall A or C needs to be running</font>--> |
− | + | ||
#*Establish good photon beam | #*Establish good photon beam | ||
#* Make sure tagger quadrupole is on (-4.2 A). | #* Make sure tagger quadrupole is on (-4.2 A). | ||
#**Insert 2*10<sup>-5</sup> RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved) | #**Insert 2*10<sup>-5</sup> RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved) | ||
#*** Typical levels are (for 2*10<sup>-5</sup> radiator, electron beam current 50 nA) | #*** Typical levels are (for 2*10<sup>-5</sup> radiator, electron beam current 50 nA) | ||
− | #****RAD102_P1= <span style="color:#ff00ff"> | + | #****RAD102_P1= <span style="color:#ff00ff">15 mrad/hr</span> (tagger area, gammas, between tagger and dump) |
− | #****RAD102_P2= <span style="color:#ff00ff"> | + | #****RAD102_P2= <span style="color:#ff00ff"> 30 mrad/hr</span> (tagger area, gammas, on goniometer) |
#****RAD102_P3= <span style="color:#ff00ff"> ~2 mrem/hr</span> (tagger area, neutrons, near electronics racks) | #****RAD102_P3= <span style="color:#ff00ff"> ~2 mrem/hr</span> (tagger area, neutrons, near electronics racks) | ||
#****RAD508_P1= <span style="color:#ff00ff">~10 mrad/hr</span> (collimator cave, gammas). | #****RAD508_P1= <span style="color:#ff00ff">~10 mrad/hr</span> (collimator cave, gammas). | ||
Line 130: | Line 148: | ||
#**Run 5 min with the 10<sup>-4</sup> radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA | #**Run 5 min with the 10<sup>-4</sup> radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA | ||
#**Run 3 min with the 3*10<sup>-4</sup> radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA | #**Run 3 min with the 3*10<sup>-4</sup> radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA | ||
− | #* Active Collimator calibration. (20 + 20 mins) | + | #* Active Collimator calibration. (20 + 20 mins). Call Hovanes. |
− | #**re-Insert the 10<sup>-4</sup> radiator (Call MCC). Use about | + | #**re-Insert the 10<sup>-4</sup> radiator (Call MCC). Use about 100 nA beam current. This will provide the Act. Col. nominal positions for its high gain values. |
− | #**Determine maximum photon beam transmission by doing 2D scans | + | #**Determine maximum photon beam transmission by doing 2D scans using the collimator x/y motions (Hovanes. 1h) |
− | #** Repeat procedure with 2*10<sup>-5</sup> radiator (Call MCC) and 50 nA beam current. | + | #** Repeat procedure with 2*10<sup>-5</sup> radiator (Call MCC) and 50 nA beam current. This will provide the Act. Col. nominal positions for its low gain values. |
− | + | #**Record on the white board what is the beam position on 5C11b and Active Collimator for optimal photon transmission, both for low and high Act. Col. gain. | |
− | + | #**Retract profiler. | |
− | #**Record on the white board what is the | + | #*Verify with MCC that position slow lock is back on (locking on Act. Col. and for values corresponding to optimal photon flux). |
− | #* | + | |
− | #*Verify with MCC that position slow lock is back on (locking on | + | |
− | + | ||
#Detector and beamline checkout. | #Detector and beamline checkout. | ||
− | #*L1 trigger | + | #*Reestablish L1 trigger Alex. Somov. 3h). |
− | #*Reestablish DAQ (Sergei, | + | #*Reestablish DAQ (Sergei, 2h). |
+ | #*Microscope commissioning. Alex Barnes (2h). | ||
#*General detector calibration (Sean Dobbs . 4h). Use 10<sup>-4</sup> radiator. Call Sean when getting ready for this task (at any hour): (703) 887-1776. | #*General detector calibration (Sean Dobbs . 4h). Use 10<sup>-4</sup> radiator. Call Sean when getting ready for this task (at any hour): (703) 887-1776. | ||
− | |||
#**Run 15 min in Long Mode. | #**Run 15 min in Long Mode. | ||
− | #* | + | #*<b>From here on, the tasks below are interspersed with data production</b> |
− | #Realign | + | #Realign 60 μm diamond (JD70-100). Later on, align new 20 μm diamond JD70-104 (Hovanes, Paul Mattione. 12h/diamond). |
− | + | #L1 trigger test for high-rate performance tests (Alex Somov. 4h+4h+4h+4h. Use up to 1.5 μA. DC off if necessary) | |
− | + | #Run PS at lower B-field (450A) for the TPol can check the low photon energy tail polarization. Use specific low-energy polarimetry trigger. (Alex Somov/Nathan Sparks. (12h+12h) | |
− | + | ||
− | #L1 trigger test for high-rate performance tests (Alex Somov. | + | |
− | + | ||
− | #Run PS at lower B-field | + | |
#DAQ high-rate performance tests (Sergei Furletov 2h) | #DAQ high-rate performance tests (Sergei Furletov 2h) | ||
− | # | + | #L3 trigger test (David Lawrence. 4h) |
− | # | + | #*[[Detailed L3 Beam Test Plan Spring 2017]] |
− | # | + | #Straight track run (16h, nominally at the end of the Spring run) |
− | #* | + | #*Ramp down solenoid magnet (2h) |
+ | #*Take straight track run data (Lubomir) | ||
#Gluex data production | #Gluex data production | ||
+ | #*Log in run information in the shift summary (make a run list). For each production run, log useful comments on DAQ comment window, see [https://halldweb.jlab.org/hdops/wiki/index.php/Best_Practices/FAQ] | ||
#*Tagger quadrupole on | #*Tagger quadrupole on | ||
#*Harp scans once a day: 15 min. | #*Harp scans once a day: 15 min. | ||
#*Empty target run every week (2h: 1<sup>-</sup> h to empty/fill back the target, 1h running). Standard production current. | #*Empty target run every week (2h: 1<sup>-</sup> h to empty/fill back the target, 1h running). Standard production current. | ||
+ | #*Long mode 10 min run. Once a week (20 min). | ||
#*Amorphous run. Every day. 1h Standard production current. Time to switch from pol. to unpol.: 10min. time to switch from unpol. to pol.: 30min. | #*Amorphous run. Every day. 1h Standard production current. Time to switch from pol. to unpol.: 10min. time to switch from unpol. to pol.: 30min. | ||
− | #*TAC runs. 2 TAC runs (one at the beginning, one in the middle of the run). (Hovanes, Alex Somov, | + | #*TAC runs. 2 TAC runs (one at the beginning, one in the middle of the run). (Hovanes, Alex Somov, 10h: 8h run with thick converter. 1<sup>-</sup> LH2 target empty). Use 3.4mm collimator with 1mm plug in (if available). |
− | #*Physics production data with diamonds and 5 mm hole. Ratio of para./transverse data: | + | #*Physics production data with diamonds and 5 mm hole. Ratio of para./transverse/45<sup>o</sup>/135<sup>o</sup> data:25/25/25/25. 2h runs <b>and no more, as it may be hard to correct for calibration drifts</b>. Switch polarization every run. Time to switch: 10min. DAQ start run overhead: 3min. |
− | #**Start run with | + | #**Start run with 60 μm diamond (JD70-100). When new 20 μm diamonds is aligned, do 2 evenings of production to assess its quality and decide what diamond should be used. |
#**Luminosity: | #**Luminosity: | ||
− | #*** | + | #***Run at about 200 nA (for 60 μm diamond JD70-100). |
− | + | ||
− | + | #Parasitic run for PrimEx detector at the end during B=0 straight track run. | |
− | + | ||
− | #Parasitic run for PrimEx detector | + | |
#Parasitic TRD run | #Parasitic TRD run | ||
− | |||
== Hall D white board (current run plan) == | == Hall D white board (current run plan) == | ||
Line 182: | Line 193: | ||
== Runplan time charts== | == Runplan time charts== | ||
*[https://halldweb.jlab.org/wiki/index.php/Spring_2017_Run_time_charts View commissioning time charts] | *[https://halldweb.jlab.org/wiki/index.php/Spring_2017_Run_time_charts View commissioning time charts] | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_1.jpg View progress on planned 1st week]. What is left to do: <font color="green"> Completed</font> | ||
+ | **<strike><font color="red"> Low energy polarimetry part 1.</font></strike> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_2.jpg View progress on planned 2nd week] What is left to do: | ||
+ | **<font color="red"> <strike> Low energy polarimetry part 2. </strike> | ||
+ | **Level-3 trigger studies. </font> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_3.jpg View progress on planned 3rd week] What is left to do: <font color="green"> Completed</font> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_4.jpg View progress on planned 4th week] What is left to do: <font color="red"> | ||
+ | **Align 17 μm diamond a day before a maintenance schedule. | ||
+ | **Take a day of data with 17 μm diamond and 3.4 mm collimator. | ||
+ | **Take a day of data with 17 μm diamond and 5mm mm collimator. </font> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_5.jpg View progress on planned 5th week] What is left to do: <font color="green"> Completed</font> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_6.jpg View progress on planned 6th week] What is left to do: <font color="red"> | ||
+ | **Long mode run. | ||
+ | **Empty target run.</font> | ||
+ | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_7.jpg 7th week] | ||
<!-- | <!-- | ||
*[https://halldweb.jlab.org/wiki/index.php/Fall_2016_Run_time_charts_progress View progress] | *[https://halldweb.jlab.org/wiki/index.php/Fall_2016_Run_time_charts_progress View progress] | ||
Line 190: | Line 216: | ||
* [http://calendar.google.com Edit Runplan google calendar] | * [http://calendar.google.com Edit Runplan google calendar] | ||
* [https://cebaf.jlab.org/files/ops/accboard/ MCC white board] | * [https://cebaf.jlab.org/files/ops/accboard/ MCC white board] | ||
− | * [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1755888890 Spreadsheet: number of triggers] | + | * [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681/edit#gid=1755888890 Spreadsheet: number of triggers] |
==Accelerator status == | ==Accelerator status == | ||
Line 197: | Line 223: | ||
==Hot Checkout == | ==Hot Checkout == | ||
− | # [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status] <span style="color:green"> | + | # [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status] <span style="color:green"> 100% ready </span>; <span style="color:#BABC3A">0% checked </span>; <span style="color:red">0% not ready </span> |
==Readiness for Fall 16 run == | ==Readiness for Fall 16 run == | ||
*Solenoid (Eugene/Beni) | *Solenoid (Eugene/Beni) | ||
+ | **<strike>Problem with ground fault detector is fixed. </strike> | ||
+ | **Solenoid to be ramp-up on Monday morning. | ||
*Surveys (Tim/Tom) | *Surveys (Tim/Tom) | ||
*DAQ (Sergei) | *DAQ (Sergei) | ||
+ | **Found the reason for the corrupted files problem and fixed it. We can run in the same way as Fall 16, or install a hardware controller which redundancy would make the data taking safer. | ||
+ | **New version of CODA is available. | ||
*Trigger (Alex S.) | *Trigger (Alex S.) | ||
*Beam line | *Beam line | ||
− | **Diamond status | + | **<strike> Diamond status: They are ready </strike> |
**Tagger hodoscope (Nathan/Franz) | **Tagger hodoscope (Nathan/Franz) | ||
+ | ***Took some data. Checks are good so far. | ||
**Tagger microscope (Alex B./Richard) | **Tagger microscope (Alex B./Richard) | ||
− | ***New | + | ***<strike>New fibers are now installed.</strike> Need to check for dead channels. |
**Goniometer (Hovanes) | **Goniometer (Hovanes) | ||
− | **Collimator, Active collimator, profiler, flux monitor (Alex B./Hovanes). | + | ***Need to reglue the diamond that fell off (J1A50 50 μm, 4×4 mm² diamond. It is unclear when it fell. Maybe this is related to the fact that Hovanes and Paul did not find the diamond with the e- beam) |
+ | **<strike>Collimator, Active collimator,</strike> profiler, flux monitor (Alex B./Hovanes). | ||
+ | ***Flux monitor not checked yet. Working on profiler software to be able to mask noisy channels. | ||
**PS system (Alex S.) | **PS system (Alex S.) | ||
**Polarimeter (M. Dugger/Nathan) | **Polarimeter (M. Dugger/Nathan) | ||
+ | ***Turned it on. Need to check that the data are good. | ||
**Target (Tim/Alexandre D.) | **Target (Tim/Alexandre D.) | ||
+ | ***Will be checked by the target group today (Thursday 26th). | ||
**TAC (Hovanes) | **TAC (Hovanes) | ||
+ | ***Not checked yet. | ||
**Slow control (Hovanes) | **Slow control (Hovanes) | ||
− | **RF (Paul Mattione) | + | ***Not checked yet. |
+ | **<strike>RF (Paul Mattione)</strike> | ||
**Radiation monitors | **Radiation monitors | ||
− | ***Downstream photon probe is broken. | + | ***<strike>OSL and dosimetry rods installed around goniometer. Photon probe put back there too.</strike> |
+ | ***<strike>Downstream photon probe is broken. </strike> | ||
+ | ***Radiation monitors are ready and checked. | ||
*Detector systems | *Detector systems | ||
**ST (Mark Ito) | **ST (Mark Ito) | ||
+ | ***ST has been turned on. Taking data for HCO. | ||
**FDC (Lubomir) | **FDC (Lubomir) | ||
+ | ***Need to start to get cosmic data | ||
**CDC (Beni) | **CDC (Beni) | ||
− | ** BCal (Elton) | + | ***<strike>There may be a leak in the gas system</strike> There was no leak. |
+ | ** BCal (Elton/Mark D.) | ||
+ | ***BCal is on and working. | ||
+ | ***Need to re-evaluate what value to use for the integration window. | ||
+ | ***Need to take pulser data. | ||
** FCal (Adesh) | ** FCal (Adesh) | ||
+ | ***19 bases were replaced on Thursday 26th. | ||
**TOF (Mark Ito/Beni/Alex. Ostrovidov) | **TOF (Mark Ito/Beni/Alex. Ostrovidov) | ||
+ | ***<strike>Need to find the optimal HV. The HV-scan data from Fall 16 is not as good as first though, in particular because some have been accidentally lost. </strike> | ||
+ | ***<strike>There was a broken ADC in slot 5. It is now replaced</strike> but it has the wrong firmware. | ||
*Online monitoring (David L.) | *Online monitoring (David L.) | ||
− | *Calibration/reconstruction/offline monitoring (Paul Mattione) | + | **Added a window with reference plots to the monitoring. |
+ | *Calibration/reconstruction/offline monitoring (Paul Mattione/ Alexander Austregesilo) | ||
+ | **Software was updated. Alexander will check if the new codes are fine. | ||
*Level 3 Trigger (David L.) | *Level 3 Trigger (David L.) | ||
*Safety documents (Beni): | *Safety documents (Beni): | ||
− | **ESAD | + | **<strike>ESAD was updated to include safety procedure for TRD and is now ready. <strike> |
− | ** | + | **</strike>RSAD <strike> |
*Hall Status/safety (Tom/Tim) | *Hall Status/safety (Tom/Tim) | ||
− | + | ||
*Other topics? | *Other topics? |
Latest revision as of 16:30, 26 November 2018
Contents
Meeting General Agenda
Run Planning Meeting Notes, Mar 9 - Mar 15, 2017
Run Planning Meeting Notes, Mar 2 - Mar 8, 2017
Run Planning Meeting Notes, Feb 23- Mar 1, 2017
Run Planning Meeting Notes, Feb 16-Feb 22, 2017
Run Planning Meeting Notes, Feb 9-Feb 15, 2017
Connect Information
To connect from the outside by phone please do the following
1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.
2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.
3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.
4.) The moderator code is 8394
Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Specific instructions for connecting from JLab's Hall D conference room:
- Turn polycon on if necessary (do it before turning the computer on)
- With the polycon, place a call at 199.48.152.152
- Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
- You may have to unmute the microphone: #*4
- Turn the computer on if needed
Beam and Hall configuration
- Beam energy expected: 11.640 GeV (value from Fall 2017 measurement).
- Solenoid on at 1350A. Any field changes should be avoided if possible.
- CW Beam current:
- Range: 1 nA-1.5 μA. 250 MHz frequency.
- Standard production running expected at ~200 nA on 4·10-4 R.L. radiator.
- RSAD limit for most of the run, excluding high intensity tests: 250 nA on 4·10-4 R.L. radiator.
- FFB on or Position Slow Lock on (FFB doesn't operate below 50nA).
- Radiators:
- Goniometer diamond radiators:
- J1a50 (50 μm - 4.1·10-4 R.L., 4×4 mm²) - old crystal - excellent rocking curve
- JD70-100 (58 μm - 4.8·10-4 R.L., 7×7 mm²) - new crystal - excellent rocking curve
- JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - new crystal - good rocking curve
- JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) - new crystal - wider rocking curve - marginally usable
- We also have one 10 μm Al radiator.
- Amorphous
- 1.64 µm Al (1.86·10-5 R.L., see study)
- 10 µm Al (11.2·10-5 R.L.)
- 30 µm Al (33.7·10-5 R.L.)
- Goniometer diamond radiators:
- Tagger quadrupole on (-4.2 A).
- Collimator hole: Both 5 mm diameter and 3.4 mm diameter. Default running: 5.0 mm
- Target: LH2 target: cryogenic target
General Information
This document describes the run plan for the Hall D Spring 2017 run.
- Schedule for the Spring 2017 run:
- Jan. 26th-Jan. 29th: Electron beam restoration
- Jan. 30th-Mar. 22nd: Hall D Spring run.
- Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery.
- overall plan and priorities:
- The first priority is to do the Halls B and C KPP (key performance parameters).
- The second priority is to finish commissioning the 5-pass separator and to ensure we can reliably run with it. This is in preparation for the Fall 17 run when all halls will be a 5-pass (Hall D at 5.5 pass).
- The above implies that Hall D should be run continuously at 5.5 pass and hence, the Hall D physics run is tie to priority #2.
- Hall B starts its KPP run (3-pass) on Feb. 3rd. With smooth running, it should achieve the KPP goals in a day or two. Then, it shuts down.
- Hall C starts its KPP run (3-pass) around March 7th. It will then continue running at 1-pass for spectrometer commissioning (if its magnets are cold and ready). Then, if time permit before the end of the spring run, they may start their physics program at 5-pass.
- Hall A will be used for its beam-dump when Hall C is down, so that a high current beam can be run in the machine when Hall B and D are running. This high current beam will stabilize the beam orbit in the machine. Hall A may take advantage of receiving beam by opportunistically running its argon experiment. In that case, it will be at 1-pass.
- Experiment: GlueX E12-06-102 Production
- Planned tests:
- High-intensity GlueX test (invasive, 3 shifts)
- TPol low energy photon run (invasive, 2 shifts)
- ComCAL(PrimeX) prototype test (parasitic)
- TRD test (parasitic)
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the commissioning:
- Thur. Jan. 26 - Sun. Jan. 29 (4 days): A. Deur (accelerator restoration)
- Mon. Jan. 30 - Wed. Feb. 8 (10 days): A. Deur
- Wed. Feb. 8 - Wed. Feb. 15 (7 days): M. Dalton (with Mon. 6th - Wed. 8th overlap)
- Wed. Feb. 15 - Wed. Feb. 22 (7 days): A. Ostrovidov (with Mon. 13th - Wed. 15th overlap)
- Wed. Feb. 22 - Wed. Mar. 1 (7 days): W. Boeglin (with Mon. 20th - Wed. 22nd overlap)
- Wed. Mar. 1 - Wed. Mar. 8: (7 days): S. Dobbs (with Mon. 27th - Wed. 1st overlap)
- Wed. Mar. 8 - Wed. Mar. 15: (7 days): R. Jones (with Mon. 6th - Wed. 8th overlap)
- Wed. Mar. 15 - Wed. Mar. 22: (7 days): D. Lawrence (with Mon. 13th - Wed. 15th overlap)
- The Run Coordinator oversees the commissioning:
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed. PDLs are:
- Benedikt Zihlmann.
- The analysis coordinator (Paul Mattione) oversees the off-line diagnostic of the different systems and analysis of the data.
- Shifts: 2 persons per shift.
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed. PDLs are:
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Daily run meetings broadcasted on Bluejeans will occur at 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Useful links:
- Accelerator schedule
- Links to previous runplans
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
- Verify electron beam quality and establish photon beam (assume 1 day).
- Ion Chambers trip threshold must be set using Al. radiators
- Tune electron beam with radiator retracted
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- RAD102_P1 ~ 10 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2 ~ 30 mrad/hr (tagger area, gammas, on goniometer).
- RAD102_P3 ~ 0.1 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1 < 0.1 mrad/hr (collimator cave, gammas).
- RAD508_P2 ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- Hall D tagger CARMS, Ion Chamber and BLM threshold for beam trips should not be changed without approval of Hall D leader.
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Establish good photon beam
- Make sure tagger quadrupole is on (-4.2 A).
- Insert 2*10-5 RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved)
- Typical levels are (for 2*10-5 radiator, electron beam current 50 nA)
- RAD102_P1= 15 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2= 30 mrad/hr (tagger area, gammas, on goniometer)
- RAD102_P3= ~2 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1= ~10 mrad/hr (collimator cave, gammas).
- RAD508_P2 < ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for 2*10-5 radiator, electron beam current 50 nA)
- Insert 2*10-5 RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved)
- Once radiation levels are good, proceed with harp scans (Hovanes/Todd. 15 min)
- Take tagger harp scans. Check consistency with Accelerator's harps. Study beam focusing
- Radiation level study (1h):
- Run 5 min without radiator (Call MCC and ask to mask the FSD each time the radiator is moved). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Run 5 min with the 10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Run 3 min with the 3*10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Active Collimator calibration. (20 + 20 mins). Call Hovanes.
- re-Insert the 10-4 radiator (Call MCC). Use about 100 nA beam current. This will provide the Act. Col. nominal positions for its high gain values.
- Determine maximum photon beam transmission by doing 2D scans using the collimator x/y motions (Hovanes. 1h)
- Repeat procedure with 2*10-5 radiator (Call MCC) and 50 nA beam current. This will provide the Act. Col. nominal positions for its low gain values.
- Record on the white board what is the beam position on 5C11b and Active Collimator for optimal photon transmission, both for low and high Act. Col. gain.
- Retract profiler.
- Verify with MCC that position slow lock is back on (locking on Act. Col. and for values corresponding to optimal photon flux).
- Detector and beamline checkout.
- Reestablish L1 trigger Alex. Somov. 3h).
- Reestablish DAQ (Sergei, 2h).
- Microscope commissioning. Alex Barnes (2h).
- General detector calibration (Sean Dobbs . 4h). Use 10-4 radiator. Call Sean when getting ready for this task (at any hour): (703) 887-1776.
- Run 15 min in Long Mode.
- From here on, the tasks below are interspersed with data production
- Realign 60 μm diamond (JD70-100). Later on, align new 20 μm diamond JD70-104 (Hovanes, Paul Mattione. 12h/diamond).
- L1 trigger test for high-rate performance tests (Alex Somov. 4h+4h+4h+4h. Use up to 1.5 μA. DC off if necessary)
- Run PS at lower B-field (450A) for the TPol can check the low photon energy tail polarization. Use specific low-energy polarimetry trigger. (Alex Somov/Nathan Sparks. (12h+12h)
- DAQ high-rate performance tests (Sergei Furletov 2h)
- L3 trigger test (David Lawrence. 4h)
- Straight track run (16h, nominally at the end of the Spring run)
- Ramp down solenoid magnet (2h)
- Take straight track run data (Lubomir)
- Gluex data production
- Log in run information in the shift summary (make a run list). For each production run, log useful comments on DAQ comment window, see [2]
- Tagger quadrupole on
- Harp scans once a day: 15 min.
- Empty target run every week (2h: 1- h to empty/fill back the target, 1h running). Standard production current.
- Long mode 10 min run. Once a week (20 min).
- Amorphous run. Every day. 1h Standard production current. Time to switch from pol. to unpol.: 10min. time to switch from unpol. to pol.: 30min.
- TAC runs. 2 TAC runs (one at the beginning, one in the middle of the run). (Hovanes, Alex Somov, 10h: 8h run with thick converter. 1- LH2 target empty). Use 3.4mm collimator with 1mm plug in (if available).
- Physics production data with diamonds and 5 mm hole. Ratio of para./transverse/45o/135o data:25/25/25/25. 2h runs and no more, as it may be hard to correct for calibration drifts. Switch polarization every run. Time to switch: 10min. DAQ start run overhead: 3min.
- Start run with 60 μm diamond (JD70-100). When new 20 μm diamonds is aligned, do 2 evenings of production to assess its quality and decide what diamond should be used.
- Luminosity:
- Run at about 200 nA (for 60 μm diamond JD70-100).
- Parasitic run for PrimEx detector at the end during B=0 straight track run.
- Parasitic TRD run
Hall D white board (current run plan)
Hall D counting room white board
Runplan time charts
- View commissioning time charts
- View progress on planned 1st week. What is left to do: Completed
Low energy polarimetry part 1.
- View progress on planned 2nd week What is left to do:
-
Low energy polarimetry part 2. - Level-3 trigger studies.
-
- View progress on planned 3rd week What is left to do: Completed
- View progress on planned 4th week What is left to do:
- Align 17 μm diamond a day before a maintenance schedule.
- Take a day of data with 17 μm diamond and 3.4 mm collimator.
- Take a day of data with 17 μm diamond and 5mm mm collimator.
- Long mode run.
- Empty target run.
- View Runplan google calendar
- Edit Runplan google calendar
- MCC white board
- Spreadsheet: number of triggers
Accelerator status
Hot Checkout
- Hot Check OUT Status 100% ready ; 0% checked ; 0% not ready
Readiness for Fall 16 run
- Solenoid (Eugene/Beni)
Problem with ground fault detector is fixed.- Solenoid to be ramp-up on Monday morning.
- Surveys (Tim/Tom)
- DAQ (Sergei)
- Found the reason for the corrupted files problem and fixed it. We can run in the same way as Fall 16, or install a hardware controller which redundancy would make the data taking safer.
- New version of CODA is available.
- Trigger (Alex S.)
- Beam line
Diamond status: They are ready- Tagger hodoscope (Nathan/Franz)
- Took some data. Checks are good so far.
- Tagger microscope (Alex B./Richard)
New fibers are now installed.Need to check for dead channels.
- Goniometer (Hovanes)
- Need to reglue the diamond that fell off (J1A50 50 μm, 4×4 mm² diamond. It is unclear when it fell. Maybe this is related to the fact that Hovanes and Paul did not find the diamond with the e- beam)
Collimator, Active collimator,profiler, flux monitor (Alex B./Hovanes).- Flux monitor not checked yet. Working on profiler software to be able to mask noisy channels.
- PS system (Alex S.)
- Polarimeter (M. Dugger/Nathan)
- Turned it on. Need to check that the data are good.
- Target (Tim/Alexandre D.)
- Will be checked by the target group today (Thursday 26th).
- TAC (Hovanes)
- Not checked yet.
- Slow control (Hovanes)
- Not checked yet.
RF (Paul Mattione)- Radiation monitors
OSL and dosimetry rods installed around goniometer. Photon probe put back there too.Downstream photon probe is broken.- Radiation monitors are ready and checked.
- Detector systems
- ST (Mark Ito)
- ST has been turned on. Taking data for HCO.
- FDC (Lubomir)
- Need to start to get cosmic data
- CDC (Beni)
There may be a leak in the gas systemThere was no leak.
- BCal (Elton/Mark D.)
- BCal is on and working.
- Need to re-evaluate what value to use for the integration window.
- Need to take pulser data.
- FCal (Adesh)
- 19 bases were replaced on Thursday 26th.
- TOF (Mark Ito/Beni/Alex. Ostrovidov)
Need to find the optimal HV. The HV-scan data from Fall 16 is not as good as first though, in particular because some have been accidentally lost.There was a broken ADC in slot 5. It is now replacedbut it has the wrong firmware.
- ST (Mark Ito)
- Online monitoring (David L.)
- Added a window with reference plots to the monitoring.
- Calibration/reconstruction/offline monitoring (Paul Mattione/ Alexander Austregesilo)
- Software was updated. Alexander will check if the new codes are fine.
- Level 3 Trigger (David L.)
- Safety documents (Beni):
ESAD was updated to include safety procedure for TRD and is now ready. <strike>- RSAD
- Hall Status/safety (Tom/Tim)
- Other topics?