== Meeting General Agenda == | == Meeting General Agenda == | ||
+ | |||
+ | [[Run Planning Meeting Notes, Mar 9 - Mar 15, 2017]] | ||
[[Run Planning Meeting Notes, Mar 2 - Mar 8, 2017]] | [[Run Planning Meeting Notes, Mar 2 - Mar 8, 2017]] | ||
Line 48: | Line 50: | ||
**We also have one 10 μm Al radiator. | **We also have one 10 μm Al radiator. | ||
**Amorphous | **Amorphous | ||
− | *** 1. | + | *** 1.64 µm Al (1.86·10<sup>-5</sup> R.L., see [https://logbooks.jlab.org/entry/3631428 study]) |
*** 10 µm Al (11.2·10<sup>-5</sup> R.L.) | *** 10 µm Al (11.2·10<sup>-5</sup> R.L.) | ||
*** 30 µm Al (33.7·10<sup>-5</sup> R.L.) | *** 30 µm Al (33.7·10<sup>-5</sup> R.L.) | ||
Line 191: | Line 193: | ||
== Runplan time charts== | == Runplan time charts== | ||
*[https://halldweb.jlab.org/wiki/index.php/Spring_2017_Run_time_charts View commissioning time charts] | *[https://halldweb.jlab.org/wiki/index.php/Spring_2017_Run_time_charts View commissioning time charts] | ||
− | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_1.jpg View progress on planned 1st week]. What is left to do: | + | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_1.jpg View progress on planned 1st week]. What is left to do: <font color="green"> Completed</font> |
− | **<font color="red"> Low energy polarimetry part 1.</font> | + | **<strike><font color="red"> Low energy polarimetry part 1.</font></strike> |
− | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_2.jpg View progress on planned 2nd week] What is left to do: <font color="red"> | + | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_2.jpg View progress on planned 2nd week] What is left to do: |
− | + | **<font color="red"> <strike> Low energy polarimetry part 2. </strike> | |
**Level-3 trigger studies. </font> | **Level-3 trigger studies. </font> | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Progress_3.jpg View progress on planned 3rd week] What is left to do: <font color="green"> Completed</font> | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_3.jpg View progress on planned 3rd week] What is left to do: <font color="green"> Completed</font> | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Progress_4.jpg View progress on planned 4th week] What is left to do: <font color="red"> | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_4.jpg View progress on planned 4th week] What is left to do: <font color="red"> | ||
− | ** | + | **Align 17 μm diamond a day before a maintenance schedule. |
**Take a day of data with 17 μm diamond and 3.4 mm collimator. | **Take a day of data with 17 μm diamond and 3.4 mm collimator. | ||
**Take a day of data with 17 μm diamond and 5mm mm collimator. </font> | **Take a day of data with 17 μm diamond and 5mm mm collimator. </font> | ||
Line 204: | Line 206: | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Progress_6.jpg View progress on planned 6th week] What is left to do: <font color="red"> | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_6.jpg View progress on planned 6th week] What is left to do: <font color="red"> | ||
**Long mode run. | **Long mode run. | ||
− | ** | + | **Empty target run.</font> |
− | * | + | *[https://halldweb.jlab.org/wiki/index.php/File:Progress_7.jpg 7th week] |
− | + | ||
− | + | ||
<!-- | <!-- | ||
*[https://halldweb.jlab.org/wiki/index.php/Fall_2016_Run_time_charts_progress View progress] | *[https://halldweb.jlab.org/wiki/index.php/Fall_2016_Run_time_charts_progress View progress] |
Latest revision as of 16:30, 26 November 2018
Contents
Meeting General Agenda
Run Planning Meeting Notes, Mar 9 - Mar 15, 2017
Run Planning Meeting Notes, Mar 2 - Mar 8, 2017
Run Planning Meeting Notes, Feb 23- Mar 1, 2017
Run Planning Meeting Notes, Feb 16-Feb 22, 2017
Run Planning Meeting Notes, Feb 9-Feb 15, 2017
Connect Information
To connect from the outside by phone please do the following
1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.
2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.
3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.
4.) The moderator code is 8394
Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Specific instructions for connecting from JLab's Hall D conference room:
- Turn polycon on if necessary (do it before turning the computer on)
- With the polycon, place a call at 199.48.152.152
- Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
- You may have to unmute the microphone: #*4
- Turn the computer on if needed
Beam and Hall configuration
- Beam energy expected: 11.640 GeV (value from Fall 2017 measurement).
- Solenoid on at 1350A. Any field changes should be avoided if possible.
- CW Beam current:
- Range: 1 nA-1.5 μA. 250 MHz frequency.
- Standard production running expected at ~200 nA on 4·10-4 R.L. radiator.
- RSAD limit for most of the run, excluding high intensity tests: 250 nA on 4·10-4 R.L. radiator.
- FFB on or Position Slow Lock on (FFB doesn't operate below 50nA).
- Radiators:
- Goniometer diamond radiators:
- J1a50 (50 μm - 4.1·10-4 R.L., 4×4 mm²) - old crystal - excellent rocking curve
- JD70-100 (58 μm - 4.8·10-4 R.L., 7×7 mm²) - new crystal - excellent rocking curve
- JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - new crystal - good rocking curve
- JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) - new crystal - wider rocking curve - marginally usable
- We also have one 10 μm Al radiator.
- Amorphous
- 1.64 µm Al (1.86·10-5 R.L., see study)
- 10 µm Al (11.2·10-5 R.L.)
- 30 µm Al (33.7·10-5 R.L.)
- Goniometer diamond radiators:
- Tagger quadrupole on (-4.2 A).
- Collimator hole: Both 5 mm diameter and 3.4 mm diameter. Default running: 5.0 mm
- Target: LH2 target: cryogenic target
General Information
This document describes the run plan for the Hall D Spring 2017 run.
- Schedule for the Spring 2017 run:
- Jan. 26th-Jan. 29th: Electron beam restoration
- Jan. 30th-Mar. 22nd: Hall D Spring run.
- Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery.
- overall plan and priorities:
- The first priority is to do the Halls B and C KPP (key performance parameters).
- The second priority is to finish commissioning the 5-pass separator and to ensure we can reliably run with it. This is in preparation for the Fall 17 run when all halls will be a 5-pass (Hall D at 5.5 pass).
- The above implies that Hall D should be run continuously at 5.5 pass and hence, the Hall D physics run is tie to priority #2.
- Hall B starts its KPP run (3-pass) on Feb. 3rd. With smooth running, it should achieve the KPP goals in a day or two. Then, it shuts down.
- Hall C starts its KPP run (3-pass) around March 7th. It will then continue running at 1-pass for spectrometer commissioning (if its magnets are cold and ready). Then, if time permit before the end of the spring run, they may start their physics program at 5-pass.
- Hall A will be used for its beam-dump when Hall C is down, so that a high current beam can be run in the machine when Hall B and D are running. This high current beam will stabilize the beam orbit in the machine. Hall A may take advantage of receiving beam by opportunistically running its argon experiment. In that case, it will be at 1-pass.
- Experiment: GlueX E12-06-102 Production
- Planned tests:
- High-intensity GlueX test (invasive, 3 shifts)
- TPol low energy photon run (invasive, 2 shifts)
- ComCAL(PrimeX) prototype test (parasitic)
- TRD test (parasitic)
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the commissioning:
- Thur. Jan. 26 - Sun. Jan. 29 (4 days): A. Deur (accelerator restoration)
- Mon. Jan. 30 - Wed. Feb. 8 (10 days): A. Deur
- Wed. Feb. 8 - Wed. Feb. 15 (7 days): M. Dalton (with Mon. 6th - Wed. 8th overlap)
- Wed. Feb. 15 - Wed. Feb. 22 (7 days): A. Ostrovidov (with Mon. 13th - Wed. 15th overlap)
- Wed. Feb. 22 - Wed. Mar. 1 (7 days): W. Boeglin (with Mon. 20th - Wed. 22nd overlap)
- Wed. Mar. 1 - Wed. Mar. 8: (7 days): S. Dobbs (with Mon. 27th - Wed. 1st overlap)
- Wed. Mar. 8 - Wed. Mar. 15: (7 days): R. Jones (with Mon. 6th - Wed. 8th overlap)
- Wed. Mar. 15 - Wed. Mar. 22: (7 days): D. Lawrence (with Mon. 13th - Wed. 15th overlap)
- The Run Coordinator oversees the commissioning:
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed. PDLs are:
- Benedikt Zihlmann.
- The analysis coordinator (Paul Mattione) oversees the off-line diagnostic of the different systems and analysis of the data.
- Shifts: 2 persons per shift.
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed. PDLs are:
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Daily run meetings broadcasted on Bluejeans will occur at 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Useful links:
- Accelerator schedule
- Links to previous runplans
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
- Verify electron beam quality and establish photon beam (assume 1 day).
- Ion Chambers trip threshold must be set using Al. radiators
- Tune electron beam with radiator retracted
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- RAD102_P1 ~ 10 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2 ~ 30 mrad/hr (tagger area, gammas, on goniometer).
- RAD102_P3 ~ 0.1 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1 < 0.1 mrad/hr (collimator cave, gammas).
- RAD508_P2 ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- Hall D tagger CARMS, Ion Chamber and BLM threshold for beam trips should not be changed without approval of Hall D leader.
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Establish good photon beam
- Make sure tagger quadrupole is on (-4.2 A).
- Insert 2*10-5 RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved)
- Typical levels are (for 2*10-5 radiator, electron beam current 50 nA)
- RAD102_P1= 15 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2= 30 mrad/hr (tagger area, gammas, on goniometer)
- RAD102_P3= ~2 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1= ~10 mrad/hr (collimator cave, gammas).
- RAD508_P2 < ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for 2*10-5 radiator, electron beam current 50 nA)
- Insert 2*10-5 RL radiator. (Call MCC and ask to mask the FSD each time the radiator is moved)
- Once radiation levels are good, proceed with harp scans (Hovanes/Todd. 15 min)
- Take tagger harp scans. Check consistency with Accelerator's harps. Study beam focusing
- Radiation level study (1h):
- Run 5 min without radiator (Call MCC and ask to mask the FSD each time the radiator is moved). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Run 5 min with the 10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Run 3 min with the 3*10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Active Collimator calibration. (20 + 20 mins). Call Hovanes.
- re-Insert the 10-4 radiator (Call MCC). Use about 100 nA beam current. This will provide the Act. Col. nominal positions for its high gain values.
- Determine maximum photon beam transmission by doing 2D scans using the collimator x/y motions (Hovanes. 1h)
- Repeat procedure with 2*10-5 radiator (Call MCC) and 50 nA beam current. This will provide the Act. Col. nominal positions for its low gain values.
- Record on the white board what is the beam position on 5C11b and Active Collimator for optimal photon transmission, both for low and high Act. Col. gain.
- Retract profiler.
- Verify with MCC that position slow lock is back on (locking on Act. Col. and for values corresponding to optimal photon flux).
- Detector and beamline checkout.
- Reestablish L1 trigger Alex. Somov. 3h).
- Reestablish DAQ (Sergei, 2h).
- Microscope commissioning. Alex Barnes (2h).
- General detector calibration (Sean Dobbs . 4h). Use 10-4 radiator. Call Sean when getting ready for this task (at any hour): (703) 887-1776.
- Run 15 min in Long Mode.
- From here on, the tasks below are interspersed with data production
- Realign 60 μm diamond (JD70-100). Later on, align new 20 μm diamond JD70-104 (Hovanes, Paul Mattione. 12h/diamond).
- L1 trigger test for high-rate performance tests (Alex Somov. 4h+4h+4h+4h. Use up to 1.5 μA. DC off if necessary)
- Run PS at lower B-field (450A) for the TPol can check the low photon energy tail polarization. Use specific low-energy polarimetry trigger. (Alex Somov/Nathan Sparks. (12h+12h)
- DAQ high-rate performance tests (Sergei Furletov 2h)
- L3 trigger test (David Lawrence. 4h)
- Straight track run (16h, nominally at the end of the Spring run)
- Ramp down solenoid magnet (2h)
- Take straight track run data (Lubomir)
- Gluex data production
- Log in run information in the shift summary (make a run list). For each production run, log useful comments on DAQ comment window, see [2]
- Tagger quadrupole on
- Harp scans once a day: 15 min.
- Empty target run every week (2h: 1- h to empty/fill back the target, 1h running). Standard production current.
- Long mode 10 min run. Once a week (20 min).
- Amorphous run. Every day. 1h Standard production current. Time to switch from pol. to unpol.: 10min. time to switch from unpol. to pol.: 30min.
- TAC runs. 2 TAC runs (one at the beginning, one in the middle of the run). (Hovanes, Alex Somov, 10h: 8h run with thick converter. 1- LH2 target empty). Use 3.4mm collimator with 1mm plug in (if available).
- Physics production data with diamonds and 5 mm hole. Ratio of para./transverse/45o/135o data:25/25/25/25. 2h runs and no more, as it may be hard to correct for calibration drifts. Switch polarization every run. Time to switch: 10min. DAQ start run overhead: 3min.
- Start run with 60 μm diamond (JD70-100). When new 20 μm diamonds is aligned, do 2 evenings of production to assess its quality and decide what diamond should be used.
- Luminosity:
- Run at about 200 nA (for 60 μm diamond JD70-100).
- Parasitic run for PrimEx detector at the end during B=0 straight track run.
- Parasitic TRD run
Hall D white board (current run plan)
Hall D counting room white board
Runplan time charts
- View commissioning time charts
- View progress on planned 1st week. What is left to do: Completed
Low energy polarimetry part 1.
- View progress on planned 2nd week What is left to do:
-
Low energy polarimetry part 2. - Level-3 trigger studies.
-
- View progress on planned 3rd week What is left to do: Completed
- View progress on planned 4th week What is left to do:
- Align 17 μm diamond a day before a maintenance schedule.
- Take a day of data with 17 μm diamond and 3.4 mm collimator.
- Take a day of data with 17 μm diamond and 5mm mm collimator.
- Long mode run.
- Empty target run.
- View Runplan google calendar
- Edit Runplan google calendar
- MCC white board
- Spreadsheet: number of triggers
Accelerator status
Hot Checkout
- Hot Check OUT Status 100% ready ; 0% checked ; 0% not ready
Readiness for Fall 16 run
- Solenoid (Eugene/Beni)
Problem with ground fault detector is fixed.- Solenoid to be ramp-up on Monday morning.
- Surveys (Tim/Tom)
- DAQ (Sergei)
- Found the reason for the corrupted files problem and fixed it. We can run in the same way as Fall 16, or install a hardware controller which redundancy would make the data taking safer.
- New version of CODA is available.
- Trigger (Alex S.)
- Beam line
Diamond status: They are ready- Tagger hodoscope (Nathan/Franz)
- Took some data. Checks are good so far.
- Tagger microscope (Alex B./Richard)
New fibers are now installed.Need to check for dead channels.
- Goniometer (Hovanes)
- Need to reglue the diamond that fell off (J1A50 50 μm, 4×4 mm² diamond. It is unclear when it fell. Maybe this is related to the fact that Hovanes and Paul did not find the diamond with the e- beam)
Collimator, Active collimator,profiler, flux monitor (Alex B./Hovanes).- Flux monitor not checked yet. Working on profiler software to be able to mask noisy channels.
- PS system (Alex S.)
- Polarimeter (M. Dugger/Nathan)
- Turned it on. Need to check that the data are good.
- Target (Tim/Alexandre D.)
- Will be checked by the target group today (Thursday 26th).
- TAC (Hovanes)
- Not checked yet.
- Slow control (Hovanes)
- Not checked yet.
RF (Paul Mattione)- Radiation monitors
OSL and dosimetry rods installed around goniometer. Photon probe put back there too.Downstream photon probe is broken.- Radiation monitors are ready and checked.
- Detector systems
- ST (Mark Ito)
- ST has been turned on. Taking data for HCO.
- FDC (Lubomir)
- Need to start to get cosmic data
- CDC (Beni)
There may be a leak in the gas systemThere was no leak.
- BCal (Elton/Mark D.)
- BCal is on and working.
- Need to re-evaluate what value to use for the integration window.
- Need to take pulser data.
- FCal (Adesh)
- 19 bases were replaced on Thursday 26th.
- TOF (Mark Ito/Beni/Alex. Ostrovidov)
Need to find the optimal HV. The HV-scan data from Fall 16 is not as good as first though, in particular because some have been accidentally lost.There was a broken ADC in slot 5. It is now replacedbut it has the wrong firmware.
- ST (Mark Ito)
- Online monitoring (David L.)
- Added a window with reference plots to the monitoring.
- Calibration/reconstruction/offline monitoring (Paul Mattione/ Alexander Austregesilo)
- Software was updated. Alexander will check if the new codes are fine.
- Level 3 Trigger (David L.)
- Safety documents (Beni):
ESAD was updated to include safety procedure for TRD and is now ready. <strike>- RSAD
- Hall Status/safety (Tom/Tim)
- Other topics?